Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.85
| 0.80 | 0.05 | $15,000.00 | $750.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.75
| 0.70 | 0.05 | $35,000.00 | $1,750.00 |
7 | OFFICE FACILITIES | 7.00 | MTH |
6.00
| 5.00 | 1.00 | $5,000.00 | $5,000.00 |
8 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $600,000.00 | $120,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.65
| 0.45 | 0.20 | $150,000.00 | $30,000.00 |
12 | CONCRETE REMOVAL (NON-REINFORCED) | 919.00 | CY |
856.70
| 739.95 | 116.75 | $195.00 | $22,766.25 |
13 | UNCLASSIFIED EXCAVATION | 2,587.00 | CY |
1,428.40
| 1,160.35 | 268.05 | $195.00 | $52,269.75 |
15 | CRUSHED MISCELLANEOUS BASE | 2,077.00 | CY |
1,010.80
| 838.11 | 172.69 | $84.00 | $14,505.96 |
21 | AC PAVEMENT(PATCH BACK) | 370.00 | TON |
343.10
| 213.79 | 129.31 | $220.00 | $28,448.20 |
34 | PCC WALK & DRIVEWAYS, 4" THICK | 17,616.00 | SF |
16,133.50
| 12,472.00 | 3,661.50 | $6.75 | $24,715.13 |
35 | PCC CURB RAMPS | 143.00 | CY |
143.00
| 115.43 | 27.57 | $775.00 | $21,366.75 |
36 | DETECTABLE WARNING SURFACE | 627.00 | SF |
627.00
| 510.00 | 117.00 | $42.00 | $4,914.00 |
37 | CROSS GUTTER | 458.00 | CY |
458.00
| 368.79 | 89.21 | $400.00 | $35,684.00 |
39 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.45 | 0.05 | $42,000.00 | $2,100.00 |
|