Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.85 | 0.05 | $15,000.00 | $750.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.85
| 0.75 | 0.10 | $35,000.00 | $3,500.00 |
7 | OFFICE FACILITIES | 7.00 | MTH |
7.00
| 6.00 | 1.00 | $5,000.00 | $5,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.80
| 0.65 | 0.15 | $150,000.00 | $22,500.00 |
14 | UNCLASSIFIED EXCAVATION (ROADWAY) | 5,774.00 | CY |
1,282.00
| 0.00 | 1,282.00 | $48.00 | $61,536.00 |
16 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 65,327.00 | SY |
15,439.00
| 0.00 | 15,439.00 | $9.50 | $146,670.50 |
17 | PORTLAND CEMENT FOR CSPB | 1,538.00 | TON |
361.23
| 0.00 | 361.23 | $210.00 | $75,858.30 |
18 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 438,548.00 | SF |
3,613.00
| 0.00 | 3,613.00 | $0.23 | $830.99 |
19 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 578,642.00 | SF |
138,950.00
| 0.00 | 138,950.00 | $0.21 | $29,179.50 |
21 | AC PAVEMENT(PATCH BACK) | 370.00 | TON |
370.00
| 343.10 | 26.90 | $220.00 | $5,918.00 |
22 | AC PAVEMENT(DIGOUTS) | 92.00 | TON |
90.00
| 0.00 | 90.00 | $155.00 | $13,950.00 |
27 | CCPRACP MIX DESIGN, SAMPLING, AND TESTING (STIPULATED UNIT PRICE OF $10000) | 1.00 | LS |
0.75
| 0.00 | 0.75 | $10,000.00 | $7,500.00 |
28 | CCPR AC PAVEMENT, 3" THICK | 65,327.00 | SY |
15,439.00
| 0.00 | 15,439.00 | $13.50 | $208,426.50 |
29 | EMULSIFIED RECYCLING AGENT | 345.00 | TON |
67.02
| 0.00 | 67.02 | $950.00 | $63,669.00 |
30 | IMPORTED RECLAIMED ASPHALT PAVEMENT (RAP) | 3,207.00 | TON |
2,421.00
| 0.00 | 2,421.00 | $40.00 | $96,840.00 |
39 | TRAFFIC CONTROL | 1.00 | LS |
0.65
| 0.50 | 0.15 | $42,000.00 | $6,300.00 |
|