Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.85 | 0.05 | $35,000.00 | $1,750.00 |
7 | OFFICE FACILITIES | 7.00 | MTH |
8.00
| 7.00 | 1.00 | $5,000.00 | $5,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.85
| 0.80 | 0.05 | $150,000.00 | $7,500.00 |
13 | UNCLASSIFIED EXCAVATION | 2,587.00 | CY |
1,550.40
| 1,428.40 | 122.00 | $195.00 | $23,790.00 |
14 | UNCLASSIFIED EXCAVATION (ROADWAY) | 5,774.00 | CY |
3,386.00
| 1,282.00 | 2,104.00 | $48.00 | $100,992.00 |
16 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 65,327.00 | SY |
40,692.00
| 15,439.00 | 25,253.00 | $9.50 | $239,903.50 |
17 | PORTLAND CEMENT FOR CSPB | 1,538.00 | TON |
952.25
| 361.23 | 591.02 | $210.00 | $124,114.20 |
19 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 578,642.00 | SF |
578,515.00
| 138,950.00 | 439,565.00 | $0.21 | $92,308.65 |
27 | CCPRACP MIX DESIGN, SAMPLING, AND TESTING (STIPULATED UNIT PRICE OF $10000) | 1.00 | LS |
0.95
| 0.75 | 0.20 | $10,000.00 | $2,000.00 |
28 | CCPR AC PAVEMENT, 3" THICK | 65,327.00 | SY |
40,692.00
| 15,439.00 | 25,253.00 | $13.50 | $340,915.50 |
29 | EMULSIFIED RECYCLING AGENT | 345.00 | TON |
172.30
| 67.02 | 105.28 | $950.00 | $100,016.00 |
39 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.65 | 0.15 | $42,000.00 | $6,300.00 |
|