Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,500.00 | $0.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
9.00
| 9.00 | 0.00 | $500.00 | $0.00 |
3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $1,000.00 | $0.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $15,000.00 | $0.00 |
5 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,500.00 | $0.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $35,000.00 | $0.00 |
7 | OFFICE FACILITIES | 7.00 | MTH |
10.00
| 10.00 | 0.00 | $5,000.00 | $0.00 |
8 | MOBILIZATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $600,000.00 | $0.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 1.00 | 0.00 | $150,000.00 | $0.00 |
10 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 14.00 | EA |
5.00
| 5.00 | 0.00 | $1,000.00 | $0.00 |
11 | TREE REMOVAL (6"-12" DIAMETER) | 1.00 | EA |
1.00
| 1.00 | 0.00 | $1,300.00 | $0.00 |
12 | CONCRETE REMOVAL (NON-REINFORCED) | 919.00 | CY |
974.64
| 974.64 | 0.00 | $195.00 | $0.00 |
13 | UNCLASSIFIED EXCAVATION | 2,587.00 | CY |
2,018.40
| 2,018.40 | 0.00 | $195.00 | $0.00 |
14 | UNCLASSIFIED EXCAVATION (ROADWAY) | 5,774.00 | CY |
5,774.00
| 5,774.00 | 0.00 | $48.00 | $0.00 |
15 | CRUSHED MISCELLANEOUS BASE | 2,077.00 | CY |
1,435.80
| 1,435.80 | 0.00 | $84.00 | $0.00 |
16 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 65,327.00 | SY |
64,324.00
| 64,324.00 | 0.00 | $9.50 | $0.00 |
17 | PORTLAND CEMENT FOR CSPB | 1,538.00 | TON |
1,506.80
| 1,506.80 | 0.00 | $210.00 | $0.00 |
18 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 438,548.00 | SF |
407,779.00
| 407,779.00 | 0.00 | $0.23 | $0.00 |
19 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 578,642.00 | SF |
578,515.00
| 578,515.00 | 0.00 | $0.21 | $0.00 |
20 | AC PAVEMENT | 338.00 | TON |
410.36
| 410.36 | 0.00 | $172.00 | $0.00 |
21 | AC PAVEMENT(PATCH BACK) | 370.00 | TON |
370.00
| 370.00 | 0.00 | $220.00 | $0.00 |
22 | AC PAVEMENT(DIGOUTS) | 92.00 | TON |
235.00
| 235.00 | 0.00 | $155.00 | $0.00 |
23 | RECONSTRUCT MANHOLE | 68.00 | EA |
61.00
| 61.00 | 0.00 | $2,500.00 | $0.00 |
24 | DOUBLE ADJUST MANHOLE | 49.00 | EA |
49.00
| 49.00 | 0.00 | $1,800.00 | $0.00 |
25 | ASPHALT RUBBER HOT MIX | 9,173.00 | TON |
9,275.20
| 9,275.20 | 0.00 | $115.00 | $0.00 |
26 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
500.00
| 500.00 | 0.00 | $134.00 | $0.00 |
27 | CCPRACP MIX DESIGN, SAMPLING, AND TESTING (STIPULATED UNIT PRICE OF $10000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $10,000.00 | $0.00 |
28 | CCPR AC PAVEMENT, 3" THICK | 65,327.00 | SY |
63,982.00
| 63,982.00 | 0.00 | $13.50 | $0.00 |
29 | EMULSIFIED RECYCLING AGENT | 345.00 | TON |
266.22
| 266.22 | 0.00 | $950.00 | $0.00 |
30 | IMPORTED RECLAIMED ASPHALT PAVEMENT (RAP) | 3,207.00 | TON |
2,421.00
| 2,421.00 | 0.00 | $40.00 | $0.00 |
31 | PCC CURB, TYPE A1-8 | 302.00 | LF |
302.00
| 302.00 | 0.00 | $37.00 | $0.00 |
32 | PCC CURB, TYPE A1-VAR | 35.00 | LF |
20.00
| 20.00 | 0.00 | $37.00 | $0.00 |
33 | PCC CURB & GUTTER, TYPE A2-8 | 2,794.00 | LF |
3,591.00
| 3,591.00 | 0.00 | $45.00 | $0.00 |
34 | PCC WALK & DRIVEWAYS, 4" THICK | 17,616.00 | SF |
17,896.50
| 17,896.50 | 0.00 | $6.75 | $0.00 |
35 | PCC CURB RAMPS | 143.00 | CY |
151.20
| 151.20 | 0.00 | $775.00 | $0.00 |
36 | DETECTABLE WARNING SURFACE | 627.00 | SF |
627.00
| 627.00 | 0.00 | $42.00 | $0.00 |
37 | CROSS GUTTER | 458.00 | CY |
458.00
| 458.00 | 0.00 | $400.00 | $0.00 |
38 | INSTALL FIRE HYDRANT LOCATION RPM | 47.00 | EA |
47.00
| 47.00 | 0.00 | $30.00 | $0.00 |
39 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 1.00 | 0.00 | $42,000.00 | $0.00 |
40 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
2.00
| 2.00 | 0.00 | $9,500.00 | $0.00 |
S-1 | MODIFY MOVE-IN PERIOD | | NWD |
80.00
| 80.00 | 0.00 | $0.00 | $0.00 |
S-2 | NON WORKING DAYS | | NWD |
9.00
| 9.00 | 0.00 | $0.00 | $0.00 |
S-3 | REMOVAL OF 9 TREES WITH STUMPS | | LS |
1.00
| 1.00 | 0.00 | $21,692.82 | $0.00 |
S-4A | TREE AND STUMP REMOVAL | | LS |
1.00
| 1.00 | 0.00 | $7,236.00 | $0.00 |
|