Road Projects

Current Projects

PROJECT NAME SCOPE OF WORK PROJECT SUMMARY START DATE FINISH DATE
Mulholland Highway and Stokes Canyon Road, et al. Cold-in-place recycling of existing asphalt concrete pavement; resurfacing of the roadway with asphalt rubber hot mix; reconstruct/upgrade guardrails. RDC0015701 8/6/18 11/7/18
U.S. 101/Palo Comado Canyon Rd Interchange Improvement (ABO)(AGH) Widen existing overcrossing from 40-feet to 76-feet to accommodate one travel lane in each direction, left-turn pockets, bike lanes, shoulders; and sidewalks. In addition, a signal will be installed at the northbound off-ramp to improve safety and circulation. RDC0016341 8/31/18 7/31/20
Ballentine Place, et al. Reconstruct and Resurface RDC0015528 6/13/18 12/19/18
Allen Avenue, et al. Resurfacing of existing asphalt concrete pavement; construction of curb and gutter, sidewalk, curb ramps, and drainage structures; landscaping; installation of striping and pavement markings; modification of traffic signals; and the performance of other appurtenant work. RDC0016069 10/22/18 2/27/19
Elizabeth Lake Road 2,453 feet West of Munz Ranch Road to 2,095 feet East of Bouquet Canyon Road Construction of cold-in-place recycled asphalt concrete, asphalt rubber hot mix, metal beam guard rail, terminal end sections, and drainage structures; installation of striping and pavement markings; and the performance of other appurtenant work. RDC0015244 5/22/18 10/25/18
Pine Canyon Road Cold-in-place recycled asphalt concrete, asphalt rubber hot mix; and the performance of other appurtenant work. RDC0014131 7/30/18 10/3/18
Athens/Westmont - Vermont Avenue Pavement Improvements The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. RMD3202003 9/3/18


Future Projects

PROJECT NAME SCOPE OF WORK PROJECT SUMMARY START DATE FINISH DATE
Wilmington Av - 200' S/o Victoria St to Del Amo Bl Road Resurfacing and Sidewalk Reconstruction RDC0015933 9/26/19 12/27/19
Santa Fe Av-Artesia Bl to Del Amo Bl Resurf and Reconst RDC0014455 2/5/20 7/29/20
Old Topanga Cyn Rd-2,723' S/o Valdez Rd/Topanga Cyn Bl Resurfacing- 1.5" mill and overlay with rubber. RDC0016306 7/8/19 8/17/19
Wilshire Boulevard, Et Al. Reconstruction of curb & gutter, sidewalk, driveways, cross gutters, and curb ramps; construction of an asphalt-rubber and aggregate membrane, concrete pavement, and drainage structures, resurfacing of existing roadway pavement with tire rubber modified asphalt concrete; traffic signal modifications; installation of striping and pavewment markkings; and the performance of other appurtenant work. RDC0015533 8/4/20 5/1/21
Washington Bl, et al. Road Resurfacing RDC0016075 7/13/20 10/11/20
Norwalk Bl, et al Reconstruct and Resurface RDC0015912 9/28/20 9/28/21
Hacienda Heights - Leticia Drive, et al. The proposed work includes cold-mill enough existing pavement to produce cold central planted recycled pavement (CCPR); pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the CCPR on CSPB to provide a long lasting finished driving surface. RMD1408001 3/5/20 6/3/20
Hazard Av, et al. Construction of tire rubber modified asphalt concrete, cold central plant recycled AC pavement, cement stabilized pulverized base, curb and gutter, curb ramps, cross gutters, sidewalk, driveways and bus pads; and the performance of other appurtenant work. RDC0016052 5/18/20 9/15/20
Long Beach Island - Harco Street, et al. The proposed work includes pulverize and stabilize the existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB) and place a layer of rubberized hot-mix asphalt over the conventional AC on CSPB to provide a long lasting finished driving surface and upgrade of ADA curb ramps. RMD4467006 5/15/19
Chatsworth - Lake Manor Drive, et al. reconstruction of roadway pavement using cold central plant recycled asphalt concrete pavement; construction of sidewalk, driveways, curb and gutter, curb ramps, and cross gutters; installation of striping and pavement markings; and the performance of other appurtenant work RMD3508001 1/9/20 4/8/20


Completed Projects

PROJECT NAME SCOPE OF WORK PROJECT SUMMARY START DATE FINISH DATE
El Segundo Boulevard - Avalon Boulevard to Central Avenue, et al. Cold-in-place recycling of existing asphalt concrete pavement; resurfacing of the roadway with asphalt rubber hot mix; reconstruction of curb and gutter, sidewalk, driveways, and curb ramps; construction of bioswales; installation of striping and pavment markings; landscaping; and the performance of other appurtenant work. RDC0014453 8/24/15 12/12/16
Firestone Boulevard - Central Avenue/Graham Avenue, et al. Resurfacing of roadway pavement; construction of an asphalt rubber and aggregate membrane interlayer; reconstruction of medians, curb and gutter, sidewalk, driveways, and curb ramps; installation of striping and pavement markings; traffic signal modifications; and the performance of other appurtenant work. RDC0014915 11/3/16 7/18/17
McDonnell Avenue, et al. Construction of asphalt rubber hot mix surface course on cold central plant recycled asphalt concrete base course, and cement-stabilized pulverized base; reconstruction of curb and gutter, sidewalk, driveways, curb ramps, alley intersections, and cross gutters; installation of striping and pavement markings; modification of traffic signals; and the performance of other appurtenant work. RDC0015818 3/20/17 10/19/17
Foothill Boulevard - Rosemead Boulevard to Michillinda Avenue, et al. Resurfacing of roadway pavement with tire rubber modified asphalt concrete on an asphalt concrete leveling course, construction of Portland cement curb and gutter, sidewalk and curb ramps, river rock paving, installation of striping and pavement markings, traffic signal modification and synchronization, and the performance of other incidental and appurtenant work. RDC0013674 2/22/17 10/17/17