LED Highway Safety Light Replacement Program

Project Overview

The most widespread lighting technology for street lighting, including the highway safety lights (HSL) at signalized intersections is High Pressure Sodium (HPS). Today, highly efficient, energy-saving Light Emitting Diode (LED) technology can replace HPS with over 50% power saving efficiency and 5 times the lamp lifespan. In addition to the benefits of energy and maintenance savings, LED lighting gives a high-quality white light where the colors of objects like cars, clothing, and landscaping can be clearly observed, improving community aesthetics.

This program will install over 2,800 HSL in Unincorporated County Areas over a two year period. Once this lighting conversion effort is complete, 1,617,000 kWh of energy will be saved every year. This amount of energy savings is enough to power 235 California households every year.

The current HPS "cobraheads" seen here:
cobra heads

Will be replaced with LED versions that may resemble one of these:
cobra heads
project status

LED HSL Installation Locations

  • Stevenson Ranch (Scheduled for Summer 2016)
  • Castaic (Scheduled for Summer 2016)
  • Canyon Country (Scheduled for Summer 2016)
  • Agua Dulce (Scheduled for Summer 2016)
  • Marina del Rey (Completed June 2014)
  • Florence/Firestone (Completed September 2014)
  • Walnut Park (Completed September 2014)
  • East Los Angeles (Completed January 2015)
  • Charter Oak Islands (Completed May 2015)
  • Covina Islands (Completed May 2015)
  • Unincorporated Covina (Completed May 2015)
  • Unincorporated Glendora (Completed May 2015)
  • Unincorporated Azusa (Completed May 2015)
  • Valinda (Completed May 2015)
  • East Valinda (Completed May 2015)
  • West Valinda (Completed May 2015)
  • San Jose Hills (Completed May 2015)
  • Bassett (Completed May 2015)
  • Avocado Heights (Completed May 2015)
  • Whittier Narrows (Completed May 2015)
  • East San Gabriel (Completed May 2015)
  • South San Gabriel (Completed May 2015)
  • North East San Gabriel (Completed May 2015)
  • San Pasqual (Completed May 2015)
  • East Pasadena (Completed May 2015)
  • Chapman Woods (Completed May 2015)
  • Michillinda Park (Completed May 2015)
  • Unincorporated Monrovia (Completed May 2015)
  • Unincorporated Arcadia (Completed May 2015)
  • Hacienda Heights (Completed November 2015)
  • Rowland Heights (Completed November 2015)
  • Unincorporated Whittier (Completed November 2015)
  • West Whittier (Completed April 2016)
  • South Whittier (Completed April 2016)
  • Los Nietos (Completed April 2016)
  • East La Mirada (Completed April 2016)

Communities will continue to be added as we progress, so check back soon, and don't forget to follow us on Twitter. #LEDHighwaySafetyLights