Lower Busch Tank Improvement

  • Project Scope:
    Construct a new steel tank and demolish the existing 300,000 gallon concrete tank.
  • Project Benefits:
    Improve water quality, system reliability, and protect the health and safety of existing customers.
  • Community Engagement:
    CEQA EIR outreach. Project information will be distributed to the community prior to construction.
  • Project Location:
    City of Malibu
  • Cost Estimate:
    - Total Project: $8,312,235 - Construction Contract: $3,366,921
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Final Plans – Oct 2025
    - Advertise for Construction Bids – Nov 2025
    - Start of Construction – Aug 2026

    Note - Dates subject to change