Lower Busch Tank Improvement
-
Project Scope:Construct a new steel tank and demolish the existing 300,000 gallon concrete tank.
-
Project Benefits:Improve water quality, system reliability, and protect the health and safety of existing customers.
-
Community Engagement:CEQA EIR outreach. Project information will be distributed to the community prior to construction.
-
Project Location:City of Malibu
-
Cost Estimate:- Total Project: $8,312,235 - Construction Contract: $3,366,921
-
Economic Impact:Project construction supports direct and indirect jobs.
-
Schedule:- Final Plans – Oct 2025
- Advertise for Construction Bids – Nov 2025
- Start of Construction – Aug 2026
Note - Dates subject to change
Please contact us with any questions about this project.
Luis Carmona, Project Manager
Office: (626) 458-4931
lcarmona@dpw.lacounty.gov
Location Map