Coastline Drive 12-Inch Waterline Improvements

  • Project Scope:
    Replace 2,000 ft. of aging waterline with a new 12-in. dia. steel waterline.
  • Project Benefits:
    Reduce the risk of leaks, improve water supply reliability, and protect the health and safety of existing customers.
  • Community Engagement:
    CEQA EIR outreach. Project information was distributed to the community prior to construction.
  • Project Location:
    Unincorporated Community of Sunset Mesa
  • Cost Estimate:
    Total Project: $6,700,000
  • Economic Impact:
    - Overall industry production value: $5,400,000 - Labor income: $1,700,000 - No. of jobs created: 16.3
  • Schedule:
    - Final Plans – Dec 2023
    - Advertise for Construction Bids – Jun 2024
    - Start of Construction – May 2025

    Note - Dates subject to change

Please contact us with any questions about this project.