PW Banner

Upper Encinal Tank Improvement

  • Project Scope:
    Replace 70,000 gal. tank with 185,000 gal. tank
  • Project Benefits:
    Improve water quality, system reliability, and protect the health and safety of existing customers.
  • Community Engagement:
    Project information will be distributed to the community prior to construction. CEQA EIR Outreach
  • Project Location:
    City of Malibu
  • Cost Estimate:
    - Total Project Cost Estimate: $7,100,000
  • Economic Impact:
    - Overall industry production value: $6,700,000 - Labor income: $2,200,000 - No. of jobs created: 20.3
  • Schedule:
    - Final Plans – Summer 2026
    - Advertise for Construction Bids – Early 2027
    - Start of Construction – Early 2028

    Note - Dates subject to change

Please contact us with any questions about this project.
Katrine Usi, Project Manager
Office: (626) 458-3117
kusi@dpw.lacounty.gov
Location Map
Map