PW Banner

Avenue J-12 and 50th Street West Site Improvements Well 4-91

  • Project Scope:
    Replacement of groundwater well, installation of ductile iron pipe, construction of a retention basin, electrical upgrades, and boundary fencing.
  • Project Benefits:
    Improves water quality and system reliability.
  • Community Engagement:
    Project information was be distributed to the community prior to construction.
  • Project Location:
    43808 N. 50th Street West, Lancaster, CA
  • Cost Estimate:
    Total Project: $9,400,000
  • Economic Impact:
    - Overall industry production value: $7,800,000 - Labor income: $2,500,000 - No. of jobs created: 23.9
  • Schedule:
    - Advertise for Construction – Sep 2024
    - Start of Construction – Nov 2025
    - End of Construction – Jan 2027

    Note - Dates subject to change

Please contact us with any questions about this project.
Kevin Montenegro, Project Manager
kmontenegro@dpw.lacounty.gov
Location Map
Map