New Sweetwater Mesa Water Tank Project
  • Project Scope:
    Construct new water storage tank on 3799 Sweetwater Mesa Road, Malibu, CA 90265
  • Project Benefits:
    Improve water quality, system reliability, and protect the health and safety of existing customers.
  • Community Outreach:
    CEQA EIR outreach. Project information will be distributed to the community prior to construction.
  • Project Location:
    City of Malibu
  • Cost Estimate:
    - Total Project: $6,700,000 - Construction: $4,000,000
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Final Plans – Spring 2025
    - Advertise for Construction Bids – Fall 2025
    - Start of Construction – Summer 2026

    Note - Dates subject to change

Please contact us with any questions about this project.
Matthew Nazaroff, Project Manager
Office: (626) 458-4952
mnazaroff@dpw.lacounty.gov
Location Map