Encinal Canyon Pressure Zones 525 and 825 Improvements
  • Project Scope:
    Replace approx. 5,800 of undersized waterline
  • Project Benefits:
    Improve water quality, system reliability, and protect the health and safety of existing customers.
  • Community Engagement:
    Project information will be distributed to the community prior to construction. CEQA EIR Outreach
  • Project Location:
    City of Malibu
  • Cost Estimate:
    - Total Project: $5,800,000
  • Economic Impact:
    - Overall industry production value: $9,900,000 - Labor income: $3,200,000 - No. of jobs created: 30.2
  • Schedule:
    - Advertise for Construction – Jul 2022
    - Start of Construction – Sep 2023
    - End of Construction – Aug 2024

    Note - Dates subject to change

Please contact us with any questions about this project.
Katrine Usi, Project Manager
Office: (626) 458-3117