Encinal Canyon Pressure Zones 525 and 825 Improvements
-
Project Scope:Replace approx. 5,800 of undersized waterline
-
Project Benefits:Improve water quality, system reliability, and protect the health and safety of existing customers.
-
Community Engagement:Project information will be distributed to the community prior to construction. CEQA EIR Outreach
-
Project Location:City of Malibu
-
Cost Estimate:- Total Project: $5,800,000
-
Economic Impact:- Overall industry production value: $9,900,000 - Labor income: $3,200,000 - No. of jobs created: 30.2
-
Schedule:- Advertise for Construction – Jul 2022
- Start of Construction – Sep 2023
- End of Construction – Feb 2025
Note - Dates subject to change
Please contact us with any questions about this project.
Katrine Usi, Project Manager
Office: (626) 458-3117
kusi@dpw.lacounty.gov
Location Map