Trancas Creek Crossing Permanent Waterline (Phase II)
-
Project Scope:Install Permanent Waterline.
-
Project Benefits:Ensure structural integrity of water main, improve water supply reliability, and protect the health and safety of existing customers.
-
Community Engagement:CEQA EIR outreach. Project information will be distributed to the community prior to construction.
-
Project Location:City of Malibu
-
Cost Estimate:- Total Project: $4,300,000 - Construction: $2,000,000
-
Economic Impact:Project construction supports direct and indirect jobs.
-
Schedule:- Final Plans – Fall 2024
- Advertise for Construction Bids – Early 2025
- Start of Construction – Fall 2025
Note - Dates subject to change
Please contact us with any questions about this project.
Victor Flores, Project Manager
Office: (626) 458-4941
vflores@dpw.lacounty.gov
Location Map