Lower Encinal Pump Station Improvements
  • Project Scope:
    Upgrade existing pump station at 4511 S. Avenida De La Encinal.
  • Project Benefits:
    Improve system reliability, water quality, and protect the health and safety of existing customers.
  • Community Engagement:
    CEQA EIR outreach. Project information will be distributed to the community prior to construction.
  • Project Location:
    City of Malibu
  • Cost Estimate:
    $1,600,000
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Final Plans – Fall 2024
    - Advertise for Construction Bids – Spring 2025
    - Start of Construction – Spring 2026

    Note - Dates subject to change

Please contact us with any questions about this project.