PCH 8-inch Waterline Improvements (Zumirez Drive to Escondido Beach Road)
  • Project Scope:
    Replace 9,600 ft. of aging 6-in. dia. waterline with a new 8-in. dia. steel waterline.
  • Project Benefits:
    Improve water quality, system reliability, and protect the health and safety of existing customers.
  • Community Outreach:
    CEQA EIR outreach (October 2020) Project information will be distributed to the community prior to final design and construction.
  • Project Location:
    City of Malibu
  • Cost Estimate:
    - Total Project: $10,000,000 - Construction: $7,300,000
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Final Plans – Summer 2024
    - Advertise for Construction Bids – Spring 2025
    - Start of Construction – Early 2026

    Note - Dates subject to change

Please contact us with any questions about this project.
Matthew Nazaroff, Project Manager
Office: (626) 458-4952