Coastline Drive 12-Inch Waterline Improvements

  • Project Scope:
    Replace 2,000 ft. of aging waterline with a new 12-in. dia. steel waterline.
  • Project Benefits:
    Reduce the risk of leaks, improve water supply reliability, and protect the health and safety of existing customers.
  • Community Engagement:
    CEQA EIR outreach. Project information will be distributed to the community prior to construction.
  • Project Location:
    Unincorporated Community of Sunset Mesa
  • Cost Estimate:
    - Total Project: $6,000,000
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Advertise for Construction – Jun 2024
    - Start of Construction – Feb 2025
    - End of Construction – Feb 2026

    Note - Dates subject to change