Fernwood Tank Improvement
  • Project Scope:
    Rehabilitate two existing 50,000 gallon tanks and improve surrounding waterlines and Entrada Pump Station.
  • Project Benefits:
    Improve water quality, system reliability, and protect the health and safety of existing customers.
  • Community Engagement:
    CEQA EIR outreach. Project information will be distributed to the community prior to construction.
  • Project Location:
    Unincorporated Topanga
  • Cost Estimate:
    $1,500,000
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Final Plans – Summer 2027
    - Advertise for Construction Bids – Spring 2028
    - Start of Construction – Late 2028

    Note - Dates subject to change