Avenue J-12 and 50th Street West Site Improvements Well 4-91
-
Project Scope:Replacement of groundwater well, installation of ductile iron pipe, construction of a retention basin, electrical upgrades, and boundary fencing.
-
Project Benefits:Improves water quality and system reliability.
-
Community Engagement:Project information will be distributed to the community prior to construction.
-
Project Location:43808 N. 50th Street West, Lancaster, CA
-
Cost Estimate:$3,711,326.00
-
Economic Impact:Project construction supports direct and indirect jobs.
-
Schedule:- Final Plans – May 2024
- Advertise for Construction Bids – Sep 2024
- Start of Construction – Sep 2025
Note - Dates subject to change
Please contact us with any questions about this project.
Abid Chowdhry, Project Manager
Office: (626) 975-3752