2309GG-001.01S1 |
Hollywood Wilshire Public Health Center Deferred Maintenance Repairs Project |
$33,599.55 |
¿ Temp Boiler |
2309GG-001.02B4 |
Hollywood Wilshire PHC Deferred Maintenance Repairs Project.. |
$238,562.94 |
¿ Mechanical System Changes ¿ DDC Controls Modifications ¿ Air Balance |
2309GG-001.03B4 |
Hollywood Wilshire Public Health Center Deferred Maintenance Repairs Project.. |
$132,294.60 |
Mechanical System Changes ¿ Air Balance |
2309GG-002.01B1 |
Los Angeles General Medical Center Linear Accelerators Equipment Replacement Project |
$2,381,388.83 |
Los Angeles General Medical Center Linear Accelerators Equipment Replacement. |
2309GG-002.02S1 |
Los Angeles General Medical Center - Linear Accelerators Equipment Replacement Project. |
$101,114.96 |
De-install and remove existing Linear Accelerator equipment. |
2309GG-007.01B1 |
Pomona Public Health Center Emergency Generator Project- |
$88,460.68 |
Transferring remaining work from work order 1920BV-032.01B1. The scope of work includes all of the exterior infrastructure work. |
2309GG-007.02S1 |
Pomona Public Health Center Emergency Generator Project. |
$1,361.74 |
Sawcut and replace the existing concrete sidewalk for conduit trenching and capping the existing irrigation lines that are crossing the trench. |
2309GG-011.01B1 |
HUCLA Pathology Lab Equipment Replacement |
$25,870.43 |
Pre-design air readings and 30-day load tests and circuit tracing as per the attached documents. |
2309GG-011.02S1 |
HUCLA Pathology Lab Equipment Replacement - Air & Electrical Reading |
$15,373.57 |
Additional Pre-design air readings as required by A/E. |
2309GG-011.03S1 |
HUCLA Pathology Lab Equipment Replacement - 72hr Load Reading |
$2,938.11 |
Additional pre-design electrical readings as required by A/E. |
2309GG-013.01B1 |
HUCLA Kitchen Grill Evaporator Cooler Replacement Air Readings |
$11,595.01 |
Pre-design air readings and 30-day load tests and circuit tracing as per the attached documents. |
2309GG-013.02S1 |
HUCLA Kitchen Grill Evaporator Cooler Replacement |
$19,296.60 |
Pre-design air readings per the A/E Pre-con requirements, HUCLA Kitchen Evap Air Project OILS dated 06/20/2024. |
2309GG-014.01S1 |
Central Public Health Center Deferred Maintenance Repairs Project |
$22,564.11 |
Modify generator pad to attach to adjacent wall structure; Scan and demo concrete protrusion at adjacent wall. |