Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $3,000) |
0.15
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.15
| 6 | MTH | $500.00 | $500.00 |
$3,000.00
| $500.00 | $500.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) |
0.10
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
001.08.005 | OFFICE FACILITIES |
0.51
| 6 | MTH | $1,700.00 | $1,750.00 |
$10,500.00
| $2,129.13 | $1,850.00 |
001.09.003 | MOBILIZATION |
7.07
| 1 | LS | $50,000.00 | $145,200.00 |
$145,200.00
| $127,292.25 | $119,350.00 |
| DISPOSAL OF HAZARDOUS MATERIALS |
0.05
| 1 | LS | $5,000.00 | $1,000.00 |
$1,000.00
| $14,810.25 | $10,000.00 |
| IMPLEMENTATION OF ENVIRONMENTAL PLANS |
0.90
| 1 | LS | $15,000.00 | $18,410.00 |
$18,410.00
| $11,536.38 | $10,500.00 |
| MISCELLANEOUS MECHANICAL WORK |
3.36
| 1 | LS | $57,000.00 | $69,100.00 |
$69,100.00
| $89,323.38 | $72,050.00 |
| OPERATIONAL TEST |
0.53
| 1 | LS | $10,000.00 | $10,900.00 |
$10,900.00
| $15,309.25 | $15,000.00 |
| MOTOR CONTROL CENTER AND SWITCHBOARD |
11.66
| 1 | LS | $371,000.00 | $239,400.00 |
$239,400.00
| $315,753.13 | $316,987.50 |
| PREPARATION OF ENVIRONMENTAL PLANS |
0.50
| 1 | LS | $5,000.00 | $10,250.00 |
$10,250.00
| $5,705.63 | $4,500.00 |
| ELECTRICAL WORK |
24.73
| 1 | LS | $524,700.00 | $507,950.00 |
$507,950.00
| $477,573.38 | $488,500.00 |
| DISCHARGE LINES STEEL PIPE SECTION REHABILITATION |
4.67
| 1 | LS | $76,000.00 | $95,980.00 |
$95,980.00
| $172,632.38 | $131,990.00 |
| ARC-FLASH AND COORDINATION STUDY |
0.61
| 1 | LS | $7,950.00 | $12,500.00 |
$12,500.00
| $8,345.25 | $7,421.00 |
| 30" VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR |
16.92
| 2 | EA | $225,703.00 | $173,740.00 |
$347,480.00
| $207,174.25 | $183,819.00 |
| 42" VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR |
25.01
| 2 | EA | $301,996.00 | $256,860.00 |
$513,720.00
| $277,830.13 | $266,430.00 |
| SOUTHERN CALIFORNIA EDISON (SCE) WORK (ALLOWANCE OF $63,600) |
3.10
| 63600 | AL | $1.00 | $1.00 |
$63,600.00
| $1.00 | $1.00 |
| Total Percent | 100 | | | | Total Amount | $2,053,990.00 | | |