Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) |
0.05
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) |
0.11
| 15 | MTH | $750.00 | $750.00 |
$11,250.00
| $750.00 | $750.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) |
0.02
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
001.06.011 | IMPLEMENTATION OF THE LTWHP |
0.05
| 1 | LS | $20,000.00 | $5,000.00 |
$5,000.00
| $27,020.00 | $40,000.00 |
001.07.003 | IMPLEMENTATION OF BMPS |
0.20
| 1 | LS | $20,000.00 | $20,000.00 |
$20,000.00
| $99,000.00 | $40,000.00 |
001.08.005 | OFFICE FACILITIES |
0.73
| 15 | MTH | $5,000.00 | $5,000.00 |
$75,000.00
| $4,003.00 | $5,000.00 |
001.09.003 | MOBILIZATION |
8.81
| 1 | LS | $500,000.00 | $900,000.00 |
$900,000.00
| $944,000.00 | $900,000.00 |
300.01.003 | CLEARING AND GRUBBING |
0.78
| 1 | LS | $12,300.00 | $80,000.00 |
$80,000.00
| $137,177.20 | $89,000.00 |
300.04.013 | STRUCTURE EXCAVATION (RETAINING WALL) |
0.19
| 194 | CY | $125.00 | $100.00 |
$19,400.00
| $105.40 | $100.00 |
300.11.017 | CONCRETED RIPRAP (LIGHT CLASS) |
0.06
| 11 | CY | $600.00 | $600.00 |
$6,600.00
| $642.00 | $600.00 |
300.13.013 | SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND TRASH |
0.17
| 47 | TON | $65.00 | $380.00 |
$17,860.00
| $274.00 | $300.00 |
301.02.003 | CRUSHED AGGREGATE BASE |
0.02
| 13 | CY | $500.00 | $190.00 |
$2,470.00
| $245.00 | $190.00 |
302.05.013 | AC PAVEMENT |
0.04
| 31 | TON | $300.00 | $140.00 |
$4,340.00
| $313.00 | $300.00 |
303.01.610 | REINFORCED CONCRETE RETAINING WALL TYPE 6 |
0.54
| 58 | CY | $1,500.00 | $950.00 |
$55,100.00
| $1,633.00 | $1,315.00 |
303.01.617 | MASONRY RETAINING WALL PER STD PLAN 618 |
0.54
| 739 | SF | $40.00 | $75.00 |
$55,425.00
| $82.80 | $80.00 |
303.01.618 | PCC FOOTING FOR MASONRY RETAINING WALL |
0.12
| 17 | CY | $750.00 | $720.00 |
$12,240.00
| $794.00 | $800.00 |
304.02.013 | CABLE RAILING (CALTRANS STD PLAN B11-47) |
0.07
| 75 | LF | $50.00 | $100.00 |
$7,500.00
| $289.80 | $154.00 |
306.01.107 | 3' - 9" W X 10' - 0" H RCB |
0.50
| 51 | LF | $1,600.00 | $1,000.00 |
$51,000.00
| $2,340.00 | $2,200.00 |
| UNCLASSIFIED EXCAVATION (DIP CROSSING) |
0.04
| 9 | CY | $400.00 | $400.00 |
$3,600.00
| $562.00 | $400.00 |
| UNCLASSIFIED EXCAVATION (LOW FLOW CHANNEL) |
0.06
| 45 | CY | $40.00 | $125.00 |
$5,625.00
| $542.00 | $300.00 |
| UNCLASSIFIED EXCAVATION (PER PLAN SH. D-9) |
0.01
| 22 | CY | $40.00 | $65.00 |
$1,430.00
| $183.20 | $71.00 |
| WELL PUMP EXPANDED METAL ENCLOSURE |
0.10
| 1 | LS | $6,000.00 | $10,000.00 |
$10,000.00
| $31,456.00 | $25,000.00 |
| WILDLIFE EXCLUSIONARY FENCING |
0.31
| 6350 | LF | $3.80 | $5.00 |
$31,750.00
| $12.60 | $10.00 |
| OUTLET STRUCTURE (UPPER DIP CROSSING) |
0.09
| 10 | CY | $2,000.00 | $960.00 |
$9,600.00
| $2,452.00 | $2,100.00 |
| PANELBOARDS |
0.10
| 1 | LS | $44,000.00 | $10,000.00 |
$10,000.00
| $13,600.00 | $15,000.00 |
| PREFABRICATED CHLORINATION BUILDING |
2.15
| 1 | LS | $42,000.00 | $220,000.00 |
$220,000.00
| $150,382.00 | $150,000.00 |
| PREPARATION OF SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $5,000) |
0.05
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
| PREPARATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.02
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| PREPARATION OF SITE SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.02
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| PREFABRICATED RESTROOM BUILDING |
0.83
| 1 | LS | $55,000.00 | $85,000.00 |
$85,000.00
| $101,385.20 | $112,926.00 |
| PREPARATION OF DEBRIS CONTAINMENT AND COLLECTION PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.02
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| PREPARATION OF FIRE PREVENTION PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.02
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| PRECAST CONCRETE WATER UTILITY VAULT |
0.10
| 1 | EA | $2,300.00 | $10,000.00 |
$10,000.00
| $21,280.00 | $22,000.00 |
| REMOVE CONCRETE RIPRAP (DIP CROSSING) |
0.05
| 17 | CY | $500.00 | $280.00 |
$4,760.00
| $779.40 | $280.00 |
| REMOVE ACTIVE 5,000 GALLONS CORRUGATED STEEL WATER TANK, FOUNDATION, AND APPURTENANCES |
0.20
| 1 | LS | $21,500.00 | $20,000.00 |
$20,000.00
| $31,640.00 | $17,500.00 |
| REINFORCED CONCRETE PAD (PER PLAN SH. D-9) |
0.08
| 7 | CY | $1,200.00 | $1,200.00 |
$8,400.00
| $890.00 | $800.00 |
| REMOVE GUNITE (DIP CROSSING) |
0.06
| 33 | CY | $250.00 | $180.00 |
$5,940.00
| $786.60 | $220.00 |
| REMOVE FUEL TANK, BOLLARDS AND SECURITY BOOTH |
0.10
| 1 | LS | $10,000.00 | $10,000.00 |
$10,000.00
| $34,480.00 | $27,000.00 |
| REMOVE GAGE BOARDS |
0.10
| 1 | LS | $40,000.00 | $10,000.00 |
$10,000.00
| $14,160.00 | $12,000.00 |
| REMOVE GASOLINE POWER GENERATOR |
0.10
| 1 | LS | $5,000.00 | $10,000.00 |
$10,000.00
| $14,360.00 | $10,000.00 |
| REMOVE GATES AND APPURTENANCES |
0.10
| 1 | LS | $17,700.00 | $10,000.00 |
$10,000.00
| $71,300.00 | $30,000.00 |
| REMOVE DECOMMISSIONED 10'-0" DIAMETER CONCRETE STEEL WATER TANK AND FOUNDATION |
0.20
| 1 | LS | $16,500.00 | $20,000.00 |
$20,000.00
| $16,160.00 | $15,000.00 |
| REMOVE DECOMMISSIONED 8'-0" DIAMETER CORRUGATED STEEL WATER TANK AND FOUNDATION |
0.20
| 1 | LS | $16,500.00 | $20,000.00 |
$20,000.00
| $24,156.00 | $15,000.00 |
| REMOVE STRUCTURE FOR PENSTOCK NO. 1 |
0.05
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $22,700.00 | $20,000.00 |
| REMOVE STAIRS AT RISER 2 |
0.05
| 1 | LS | $10,000.00 | $5,000.00 |
$5,000.00
| $20,900.00 | $15,800.00 |
| REMOVE PLATFORM AND STAIRS AT RISER 1 |
0.05
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $22,100.00 | $22,000.00 |
| REMOVE PORTABLE RESTROOM AND STEEL OVERHANG STRUCTURE |
0.10
| 1 | LS | $10,000.00 | $10,000.00 |
$10,000.00
| $18,380.00 | $10,000.00 |
| REMOVE INLET STRUCTURE FOR SLUICEWAY |
0.05
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $19,190.00 | $14,950.00 |
| RISER 1 PLATFORM 3 |
0.15
| 1 | LS | $15,940.00 | $15,000.00 |
$15,000.00
| $56,215.00 | $22,075.00 |
| RISER 1 PLATFORM 4 |
0.34
| 1 | LS | $53,140.00 | $35,000.00 |
$35,000.00
| $69,815.20 | $42,076.00 |
| RISER 1 STAIRS |
0.20
| 1 | LS | $139,200.00 | $20,000.00 |
$20,000.00
| $81,825.40 | $75,000.00 |
| RISER 2 HANDRAILS FOR STAIRS AND PLATFORM |
0.23
| 235 | LF | $120.00 | $100.00 |
$23,500.00
| $230.40 | $200.00 |
| RISER 2 PLATFORM 1 |
0.27
| 1 | LS | $55,400.00 | $28,000.00 |
$28,000.00
| $67,867.20 | $39,336.00 |
| RISER 2 PLATFORM 2 |
0.20
| 1 | LS | $36,800.00 | $20,000.00 |
$20,000.00
| $59,172.60 | $31,863.00 |
| RISER 2 STAIRS |
0.20
| 1 | LS | $80,350.00 | $20,000.00 |
$20,000.00
| $72,985.40 | $54,927.00 |
| RISER 1 HANDRAILS FOR STAIRS AND PLATFORM |
0.31
| 318 | LF | $120.00 | $100.00 |
$31,800.00
| $272.20 | $200.00 |
| RESTROOM FOUNDATION AND PLATFORM |
0.34
| 1 | LS | $134,000.00 | $35,000.00 |
$35,000.00
| $52,400.00 | $58,000.00 |
| REMOVE WATERLINE SYSTEM |
0.20
| 1 | LS | $25,000.00 | $20,000.00 |
$20,000.00
| $96,040.00 | $52,200.00 |
| REMOVE TRASHRACK AND APPURTENANCES |
0.05
| 1 | LS | $8,000.00 | $5,000.00 |
$5,000.00
| $19,510.00 | $9,000.00 |
| RISER 1 PLATFORM 1 |
0.24
| 1 | LS | $31,300.00 | $25,000.00 |
$25,000.00
| $73,778.00 | $25,000.00 |
| RISER 1 PLATFORM 2 |
0.20
| 1 | LS | $30,100.00 | $20,000.00 |
$20,000.00
| $72,778.00 | $21,890.00 |
| SLUICEWAY PIPE REPAIR |
1.27
| 1 | LS | $77,500.00 | $130,000.00 |
$130,000.00
| $115,140.00 | $130,000.00 |
| SHORING OF OPEN EXCAVATIONS |
0.10
| 1 | LS | $50,000.00 | $10,000.00 |
$10,000.00
| $93,400.00 | $75,000.00 |
| SERVICE ENTRANCE PANELS |
0.10
| 1 | LS | $36,000.00 | $10,000.00 |
$10,000.00
| $107,260.00 | $123,000.00 |
| SCE SERVICE FEE (ALLOWANCE OF $175,000) |
1.71
| 175000 | AL | $1.00 | $1.00 |
$175,000.00
| $1.00 | $1.00 |
| STRUCTURE BACKFILL (CONCRETE APRON IN FRONT OF SLUICEWAY) |
0.06
| 12 | CY | $250.00 | $500.00 |
$6,000.00
| $335.00 | $300.00 |
| STILLING WELL AND GAGE BOARDS WITH CONCRETE FOOTINGS |
0.59
| 1 | LS | $125,000.00 | $60,000.00 |
$60,000.00
| $228,460.00 | $150,000.00 |
| STAINLESS STEEL TRASHRACK |
0.39
| 1 | LS | $75,000.00 | $40,000.00 |
$40,000.00
| $111,218.20 | $111,091.00 |
| STANDBY DIESEL ENGINE GENERATOR SYSTEM |
1.17
| 1 | LS | $153,000.00 | $120,000.00 |
$120,000.00
| $174,000.00 | $154,000.00 |
| SLIPLINING OF EXISTING OUTLET TUNNEL |
0.24
| 1 | LS | $50,000.00 | $25,000.00 |
$25,000.00
| $109,312.00 | $100,000.00 |
| SLUICEWAY 36" X 36" RCB DEMOLITION AND PARTIAL PIPE REMOVAL |
0.20
| 1 | LS | $32,500.00 | $20,000.00 |
$20,000.00
| $54,500.00 | $35,000.00 |
| SLUICEWAY CHARGE LINE, JET FLOW DRAIN LINE, VALVES, AND INSPECTION |
0.98
| 1 | LS | $58,000.00 | $100,000.00 |
$100,000.00
| $113,090.30 | $100,000.00 |
| STRUCTURE EXCAVATION (RESTROOM FOOTING) |
0.04
| 9 | CY | $125.00 | $500.00 |
$4,500.00
| $307.40 | $100.00 |
| UTILITY SERVICE WORK PER PLAN SH. U-1 TO U-15 |
15.66
| 1 | LS | $1,283,000.00 | $1,600,000.00 |
$1,600,000.00
| $842,650.20 | $723,251.00 |
| STRUCTURE EXCAVATION (CONCRETE APRON IN FRONT OF SLUICEWAY) |
0.03
| 17 | CY | $300.00 | $200.00 |
$3,400.00
| $219.40 | $200.00 |
| STRUCTURE EXCAVATION (DIP CROSSING) |
0.63
| 640 | CY | $100.00 | $100.00 |
$64,000.00
| $80.60 | $90.00 |
| UNCLASSIFIED FILL (ACCESS ROAD AND LOW FLOW CHANNEL) |
0.59
| 2427 | CY | $30.00 | $25.00 |
$60,675.00
| $38.00 | $25.00 |
| UNCLASSIFIED FILL (DIP CROSSING) |
0.04
| 30 | CY | $200.00 | $130.00 |
$3,900.00
| $115.00 | $100.00 |
| UNCLASSIFIED FILL (PER PLAN SH. D-9) |
0.04
| 30 | CY | $75.00 | $130.00 |
$3,900.00
| $117.00 | $100.00 |
| UNCLASSIFIED FILL (SLUICEWAY) |
0.28
| 810 | CY | $200.00 | $35.00 |
$28,350.00
| $56.00 | $50.00 |
| UNCLASSIFIED EXCAVATION (SLUICEWAY) |
0.02
| 100 | CY | $120.00 | $25.00 |
$2,500.00
| $116.40 | $100.00 |
| UNCLASSIFIED EXCAVATION (ACCESS ROAD) |
1.38
| 4700 | CY | $40.00 | $30.00 |
$141,000.00
| $38.60 | $30.00 |
| UNCLASSIFIED EXCAVATION (CONCRETE APRON IN FRONT OF SLUICEWAY) |
0.05
| 13 | CY | $150.00 | $400.00 |
$5,200.00
| $878.00 | $400.00 |
| 1,500 GALLON SEWAGE HOLDING TANK AND APPURTENANCES |
0.49
| 1 | LS | $5,000.00 | $50,000.00 |
$50,000.00
| $55,751.60 | $42,000.00 |
| 36" STEEL PIPE AND ENCASEMENT FOR SLUICEWAY |
3.08
| 150 | LF | $250.00 | $2,100.00 |
$315,000.00
| $2,076.40 | $1,600.00 |
| 24" X 30" SLIDE GATE AND ACTUATOR AT PENSTOCK NO. 2 |
0.29
| 1 | LS | $30,000.00 | $30,000.00 |
$30,000.00
| $57,240.00 | $30,000.00 |
| 24" ACCESS PORT WITH DAVIT HOIST |
0.39
| 2 | EA | $10,000.00 | $20,000.00 |
$40,000.00
| $96,425.00 | $30,000.00 |
| 24" CIDH PILES |
0.27
| 160 | LF | $500.00 | $175.00 |
$28,000.00
| $520.20 | $395.00 |
| 5,000 GALLON WATER TANK AND ACCESSORIES |
0.73
| 1 | LS | $15,700.00 | $75,000.00 |
$75,000.00
| $112,120.00 | $75,000.00 |
| 36" X 36" CAST IRON SLIDE GATE |
0.78
| 2 | EA | $48,300.00 | $40,000.00 |
$80,000.00
| $134,434.00 | $125,000.00 |
| 36" JET FLOW GATE VALVE |
4.89
| 1 | LS | $229,000.00 | $500,000.00 |
$500,000.00
| $538,000.00 | $570,000.00 |
| 8" TRENCH DRAIN SYSTEM |
0.01
| 1 | LS | $7,500.00 | $1,000.00 |
$1,000.00
| $37,240.00 | $15,000.00 |
| AIR VENT PIPE AND FITTINGS FOR SLUICEWAY INLET STRUCTURE |
0.20
| 1 | LS | $35,000.00 | $20,000.00 |
$20,000.00
| $93,314.00 | $82,970.00 |
| AUTOMATIC TRANSFER SWITCH |
0.15
| 2 | EA | $20,000.00 | $7,500.00 |
$15,000.00
| $9,340.00 | $8,000.00 |
| ARCH 3 LOWER STAIRS MODIFICATION |
0.20
| 1 | LS | $5,000.00 | $20,000.00 |
$20,000.00
| $45,260.00 | $25,000.00 |
| CCTV AND INTERCOM SYSTEM |
3.42
| 1 | LS | $130,000.00 | $350,000.00 |
$350,000.00
| $136,740.00 | $84,700.00 |
| CLEAN AND PAINT EXISTING STRUCTURAL STEEL |
5.87
| 1 | LS | $1,580,000.00 | $600,000.00 |
$600,000.00
| $598,480.00 | $640,000.00 |
| CHECK DAM CONCRETE PLATFORM |
0.34
| 1 | LS | $90,000.00 | $35,000.00 |
$35,000.00
| $44,200.00 | $38,500.00 |
| CHECK DAM CONCRETE PLATFORM HANDRAILS |
0.08
| 78 | LF | $120.00 | $100.00 |
$7,800.00
| $445.80 | $322.00 |
| CHECK DAM STEEL HANDRAILS FOR STAIRS AND PLATFORMS |
0.13
| 136 | LF | $120.00 | $100.00 |
$13,600.00
| $515.80 | $500.00 |
| CHECK DAM STEEL STAIRS AND PLATFORMS |
0.39
| 1 | LS | $117,000.00 | $40,000.00 |
$40,000.00
| $231,006.20 | $140,000.00 |
| CONCRETE REMOVAL (REINFORCED - DIP CROSSING) |
0.01
| 6 | CY | $400.00 | $130.00 |
$780.00
| $957.20 | $450.00 |
| CHLORINATION BUILDING FOUNDATION |
0.15
| 1 | LS | $43,000.00 | $15,000.00 |
$15,000.00
| $21,239.40 | $23,637.00 |
| CHLORINATION SYSTEM |
0.20
| 1 | LS | $9,300.00 | $20,000.00 |
$20,000.00
| $54,090.00 | $42,000.00 |
| CONCRETE PIPE SUPPORT COLUMNS |
0.64
| 1 | LS | $6,500.00 | $65,000.00 |
$65,000.00
| $117,880.00 | $54,600.00 |
| CONCRETE REMOVAL (NON-REINFORCED - DIP CROSSING) |
0.04
| 32 | CY | $300.00 | $130.00 |
$4,160.00
| $772.40 | $200.00 |
| CONTROL PANELS |
0.68
| 1 | LS | $255,000.00 | $70,000.00 |
$70,000.00
| $34,640.00 | $24,200.00 |
| DRILL AND BOND DOWELS (CHECK DAM) |
0.01
| 50 | LF | $300.00 | $25.00 |
$1,250.00
| $189.70 | $150.00 |
| DRAIN PIT |
0.49
| 1 | LS | $25,000.00 | $50,000.00 |
$50,000.00
| $35,068.00 | $36,000.00 |
| FACILITY WATER DISTRIBUTION PIPING |
1.47
| 1 | LS | $200,000.00 | $150,000.00 |
$150,000.00
| $649,142.00 | $207,710.00 |
| EXPANSION JOINTS (DIP CROSSING) |
0.02
| 37 | LF | $50.00 | $45.00 |
$1,665.00
| $160.00 | $125.00 |
| ELECTRICAL WORK |
14.68
| 1 | LS | $1,263,200.00 | $1,500,000.00 |
$1,500,000.00
| $2,695,600.00 | $3,000,000.00 |
| ELECTRIC MOTOR OPERATOR AND APPURTENANCES |
0.49
| 1 | LS | $40,000.00 | $50,000.00 |
$50,000.00
| $57,600.00 | $50,000.00 |
| DROP STRUCTURE (DIP CROSSING) |
0.47
| 58 | CY | $1,750.00 | $820.00 |
$47,560.00
| $1,665.00 | $1,200.00 |
| HYDRAULIC PIPES ENCLOSURE |
0.20
| 1 | LS | $20,000.00 | $20,000.00 |
$20,000.00
| $99,009.40 | $50,000.00 |
| HYDRAULIC POWER SYSTEM |
0.98
| 1 | LS | $370,000.00 | $100,000.00 |
$100,000.00
| $524,754.00 | $425,000.00 |
| HAULING, SPREADING AND COMPACTION AT SEDIMENT PLACEMENT SITE |
1.29
| 3300 | TON | $50.00 | $40.00 |
$132,000.00
| $54.20 | $55.00 |
| FRONTIER SERVICE FEE (ALLOWANCE OF $90,000) |
0.88
| 90000 | AL | $1.00 | $1.00 |
$90,000.00
| $1.00 | $1.00 |
| IMPLEMENTATION OF THE DIVERSION OF WATER PLAN |
1.37
| 1 | LS | $240,000.00 | $140,000.00 |
$140,000.00
| $322,968.00 | $145,000.00 |
| IMPLEMENTATION OF FIRE PREVENTION PLAN |
0.24
| 1 | LS | $10,000.00 | $25,000.00 |
$25,000.00
| $42,600.00 | $25,000.00 |
| IMPLEMENTATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN |
0.10
| 1 | LS | $10,000.00 | $10,000.00 |
$10,000.00
| $39,600.00 | $25,000.00 |
| IMPLEMENTATION OF SITE SPECIFIC LEAD COMPLIANCE PLAN |
0.20
| 1 | LS | $15,000.00 | $20,000.00 |
$20,000.00
| $28,000.00 | $20,000.00 |
| IMPLEMENTATION OF DEBRIS CONTAINMENT AND COLLECTION PLAN |
0.05
| 1 | LS | $10,000.00 | $5,000.00 |
$5,000.00
| $44,600.00 | $30,000.00 |
| INLET STRUCTURE FOR SLUICEWAY (WINGWALLS AND APRON) |
0.28
| 1 | LS | $90,400.00 | $29,000.00 |
$29,000.00
| $106,765.60 | $82,125.00 |
| ITEM 15 DELETED |
0
| 1 | LS | $1.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| ITEM 16 DELETED |
0
| 1 | LS | $1.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| INLET STRUCTURE FOR PENSTOCK NO. 1 |
0.14
| 1 | LS | $36,200.00 | $14,000.00 |
$14,000.00
| $47,784.00 | $50,000.00 |
| LOW FLOW DRAIN 6" FLEXIBLE DISCHARGE PIPING AND PIPE FITTINGS |
0.05
| 1 | LS | $8,000.00 | $5,000.00 |
$5,000.00
| $44,708.00 | $10,000.00 |
| MISCELLANEOUS MECHANICAL WORK |
5.93
| 1 | LS | $90,000.00 | $606,000.00 |
$606,000.00
| $227,910.00 | $150,000.00 |
| MODIFICATION TO SPILL CONTAINMENT STRUCTURE (GENERATOR) AND BOLLARDS |
0.20
| 1 | LS | $5,920.00 | $20,000.00 |
$20,000.00
| $24,364.00 | $20,000.00 |
| OBJECT MARKER (CALTRANS STD PLAN A73A) |
0
| 8 | EA | $100.00 | $50.00 |
$400.00
| $665.60 | $200.00 |
| OPERATIONAL TESTS |
0.05
| 1 | LS | $20,000.00 | $5,000.00 |
$5,000.00
| $53,640.00 | $12,000.00 |
| OUTLET STRUCTURE (LOWER DIP CROSSING) |
0.09
| 10 | CY | $2,000.00 | $910.00 |
$9,100.00
| $2,272.00 | $2,000.00 |
| Total Percent | 100 | | | | Total Amount | $10,219,330.00 | | |