Bid Price History

Morris Dam Low Flow Outlet and Facility Improvement
$2,079,111.44
03/12/2019
539 (B7),539 (E4),539 (C7)
6
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.10 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) 0.10 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.07.003IMPLEMENTATION OF BMPS 2.50 1LS$10,000.00$51,949.74 $51,949.74 $21,355.96$16,343.00
001.08.005OFFICE FACILITIES 1.14 5MTH$2,500.00$4,738.80 $23,694.00 $4,323.13$4,200.00
001.09.003MOBILIZATION 3.28 1LS$60,000.00$68,115.79 $68,115.79 $125,612.30$100,500.00
300.01.003CLEARING AND GRUBBING 0.62 1LS$10,000.00$12,873.99 $12,873.99 $37,807.33$9,537.00
300.01.067CONCRETE REMOVAL (REINFORCED) 1.39 12CY$500.00$2,414.53 $28,974.36 $2,293.76$2,257.27
304.02.007METAL HAND RAILINGS PER STD PLAN 606 2.69 90LF$200.00$621.12 $55,900.80 $342.35$300.00
 CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) 0.12 5MTH$500.00$500.00 $2,500.00 $500.00$500.00
 ELECTROMAGNETIC GATE LOCK 0.18 1LS$1,000.00$3,684.30 $3,684.30 $3,031.05$3,050.00
 ELECTRICAL WORK 7.14 1LS$75,000.00$148,470.75 $148,470.75 $178,123.13$181,500.00
 DRIVEWAY ALARM AND VEHICLE DETECTOR SYSTEM 6.68 1LS$1,000.00$138,900.91 $138,900.91 $27,736.49$3,800.00
 DOORS AND WINDOW 1.24 1LS$8,000.00$25,692.97 $25,692.97 $23,924.50$21,996.49
 DISPOSAL OF LEAD WASTE 0.41 1LS$4,000.00$8,493.75 $8,493.75 $10,356.46$9,131.88
 GUIDE TRACK RAILS FOR SELF-ADJUSTING FLOATING BOAT DOCK 11.50 1LS$474,307.00$239,047.80 $239,047.80 $340,716.97$318,577.50
 GALVANIZED STEEL PEDESTRIAN GATE-9 FEET HIGH, 4' WIDE 0.28 1LS$1,200.00$5,871.95 $5,871.95 $8,874.16$8,236.50
 GALVANIZED STEEL PICKET FENCE-9 FEET HIGH 0.37 11LF$300.00$696.81 $7,664.91 $969.64$942.50
 GALVANIZED STEEL SWING GATE-9 FEET HIGH, 18 FEET LONG 0.59 1LS$22,000.00$12,295.58 $12,295.58 $22,223.10$22,088.00
 IMPLEMENTATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN 1.84 1LS$5,000.00$38,261.25 $38,261.25 $16,307.54$15,000.00
 IMPLEMENTATION OF SITE SPECIFIC LEAD COMPLIANCE PLAN 0.53 1LS$15,000.00$11,010.00 $11,010.00 $21,961.00$15,000.00
 IMPLEMENTATION OF DEBRIS CONTAINMENT AND COLLECTION PLAN 2.16 1LS$5,000.00$44,888.82 $44,888.82 $20,537.64$16,668.50
 KEYPAD, BOLLARDS AND FOUNDATION PER DETAIL "S1" 0.77 1LS$16,000.00$16,061.10 $16,061.10 $10,885.68$8,780.00
 JOBS COORDINATOR 1.01 1LS$20,000.00$21,000.00 $21,000.00 $14,916.50$14,399.50
 MISCELLANEOUS MECHANICAL WORK 6.43 1LS$25,000.00$133,655.70 $133,655.70 $76,938.12$81,500.00
 MOTION ACTIVATED LIGHTING 0.20 1LS$1,500.00$4,171.56 $4,171.56 $6,497.43$5,135.78
 MOTION ACTIVATED LIGHTING POLE 0.45 1LS$1,000.00$9,430.27 $9,430.27 $7,544.38$6,650.00
 MODULAR FLOATING BOAT DOCK 2.83 1LS$28,223.00$58,812.30 $58,812.30 $44,566.72$40,744.00
 PREPARATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3,000) 0.14 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
 PREPARATION OF SITE SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3,000) 0.14 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
 PREPARATION OF DEBRIS CONTAINMENT AND COLLECTION PLAN (STIPULATED UNIT PRICE OF $2,000) 0.10 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
 RECONSTRUCT MANHOLE (FIBERGLASS) 0.71 1LS$1,500.00$14,835.90 $14,835.90 $10,526.48$12,100.00
 REMOVE AND DISPOSE OF EXISTING METAL HAND RAILINGS 0.34 90LF$50.00$78.38 $7,054.20 $56.15$50.00
 CONCRETE SADDLE MODIFICATION, CONCRETE PLATFORM AND HANDRAIL 3.06 1LS$50,000.00$63,577.67 $63,577.67 $117,671.61$129,790.50
 CATERPILLAR GATE SYSTEM REPAIR AND REFURBISHMENT 8.08 1LS$328,587.00$168,055.01 $168,055.01 $206,343.84$205,300.00
 CHAIN LINK FENCE, 5' HIGH WITH BARBED WIRE 0.28 10LF$100.00$573.70 $5,737.00 $378.78$278.50
 AUTOMATIC SWING GATE OPERATOR 1.17 1LS$25,000.00$24,224.89 $24,224.89 $26,131.98$25,612.45
 20" STEEL PIPE, PIPE FITTINGS, FLEX COUPLINGS, AND PIPE FLANGES 5.80 1LS$200,304.00$120,517.11 $120,517.11 $184,134.19$179,444.00
 20" BONNETED KNIFE GATE VALVES AND ELECTRIC ACTUATORS 8.89 2EA$152,884.00$92,390.30 $184,780.60 $165,929.55$147,500.00
 3" BYPASS LINE PIPE, FITTING, BALL VALVE, AND AIR VALVE 1.37 1LS$14,497.00$28,392.85 $28,392.85 $16,538.48$17,119.00
 16" PLUNGER VALVE AND ELECTRIC ACTUATOR 12.58 1LS$107,155.00$261,495.45 $261,495.45 $261,344.58$284,333.73
 STRUCTURE CONCRETE (INCLUDING REINFORCEMENT) 0.82 12CY$2,000.00$1,418.18 $17,018.16 $2,371.53$2,200.00
 Total Percent100   Total Amount$2,079,111.44