Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) |
0.10
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) |
0.10
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
001.07.003 | IMPLEMENTATION OF BMPS |
2.50
| 1 | LS | $10,000.00 | $51,949.74 |
$51,949.74
| $21,355.96 | $16,343.00 |
001.08.005 | OFFICE FACILITIES |
1.14
| 5 | MTH | $2,500.00 | $4,738.80 |
$23,694.00
| $4,323.13 | $4,200.00 |
001.09.003 | MOBILIZATION |
3.28
| 1 | LS | $60,000.00 | $68,115.79 |
$68,115.79
| $125,612.30 | $100,500.00 |
300.01.003 | CLEARING AND GRUBBING |
0.62
| 1 | LS | $10,000.00 | $12,873.99 |
$12,873.99
| $37,807.33 | $9,537.00 |
300.01.067 | CONCRETE REMOVAL (REINFORCED) |
1.39
| 12 | CY | $500.00 | $2,414.53 |
$28,974.36
| $2,293.76 | $2,257.27 |
304.02.007 | METAL HAND RAILINGS PER STD PLAN 606 |
2.69
| 90 | LF | $200.00 | $621.12 |
$55,900.80
| $342.35 | $300.00 |
| CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) |
0.12
| 5 | MTH | $500.00 | $500.00 |
$2,500.00
| $500.00 | $500.00 |
| ELECTROMAGNETIC GATE LOCK |
0.18
| 1 | LS | $1,000.00 | $3,684.30 |
$3,684.30
| $3,031.05 | $3,050.00 |
| ELECTRICAL WORK |
7.14
| 1 | LS | $75,000.00 | $148,470.75 |
$148,470.75
| $178,123.13 | $181,500.00 |
| DRIVEWAY ALARM AND VEHICLE DETECTOR SYSTEM |
6.68
| 1 | LS | $1,000.00 | $138,900.91 |
$138,900.91
| $27,736.49 | $3,800.00 |
| DOORS AND WINDOW |
1.24
| 1 | LS | $8,000.00 | $25,692.97 |
$25,692.97
| $23,924.50 | $21,996.49 |
| DISPOSAL OF LEAD WASTE |
0.41
| 1 | LS | $4,000.00 | $8,493.75 |
$8,493.75
| $10,356.46 | $9,131.88 |
| GUIDE TRACK RAILS FOR SELF-ADJUSTING FLOATING BOAT DOCK |
11.50
| 1 | LS | $474,307.00 | $239,047.80 |
$239,047.80
| $340,716.97 | $318,577.50 |
| GALVANIZED STEEL PEDESTRIAN GATE-9 FEET HIGH, 4' WIDE |
0.28
| 1 | LS | $1,200.00 | $5,871.95 |
$5,871.95
| $8,874.16 | $8,236.50 |
| GALVANIZED STEEL PICKET FENCE-9 FEET HIGH |
0.37
| 11 | LF | $300.00 | $696.81 |
$7,664.91
| $969.64 | $942.50 |
| GALVANIZED STEEL SWING GATE-9 FEET HIGH, 18 FEET LONG |
0.59
| 1 | LS | $22,000.00 | $12,295.58 |
$12,295.58
| $22,223.10 | $22,088.00 |
| IMPLEMENTATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN |
1.84
| 1 | LS | $5,000.00 | $38,261.25 |
$38,261.25
| $16,307.54 | $15,000.00 |
| IMPLEMENTATION OF SITE SPECIFIC LEAD COMPLIANCE PLAN |
0.53
| 1 | LS | $15,000.00 | $11,010.00 |
$11,010.00
| $21,961.00 | $15,000.00 |
| IMPLEMENTATION OF DEBRIS CONTAINMENT AND COLLECTION PLAN |
2.16
| 1 | LS | $5,000.00 | $44,888.82 |
$44,888.82
| $20,537.64 | $16,668.50 |
| KEYPAD, BOLLARDS AND FOUNDATION PER DETAIL "S1" |
0.77
| 1 | LS | $16,000.00 | $16,061.10 |
$16,061.10
| $10,885.68 | $8,780.00 |
| JOBS COORDINATOR |
1.01
| 1 | LS | $20,000.00 | $21,000.00 |
$21,000.00
| $14,916.50 | $14,399.50 |
| MISCELLANEOUS MECHANICAL WORK |
6.43
| 1 | LS | $25,000.00 | $133,655.70 |
$133,655.70
| $76,938.12 | $81,500.00 |
| MOTION ACTIVATED LIGHTING |
0.20
| 1 | LS | $1,500.00 | $4,171.56 |
$4,171.56
| $6,497.43 | $5,135.78 |
| MOTION ACTIVATED LIGHTING POLE |
0.45
| 1 | LS | $1,000.00 | $9,430.27 |
$9,430.27
| $7,544.38 | $6,650.00 |
| MODULAR FLOATING BOAT DOCK |
2.83
| 1 | LS | $28,223.00 | $58,812.30 |
$58,812.30
| $44,566.72 | $40,744.00 |
| PREPARATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3,000) |
0.14
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| PREPARATION OF SITE SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3,000) |
0.14
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| PREPARATION OF DEBRIS CONTAINMENT AND COLLECTION PLAN (STIPULATED UNIT PRICE OF $2,000) |
0.10
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
| RECONSTRUCT MANHOLE (FIBERGLASS) |
0.71
| 1 | LS | $1,500.00 | $14,835.90 |
$14,835.90
| $10,526.48 | $12,100.00 |
| REMOVE AND DISPOSE OF EXISTING METAL HAND RAILINGS |
0.34
| 90 | LF | $50.00 | $78.38 |
$7,054.20
| $56.15 | $50.00 |
| CONCRETE SADDLE MODIFICATION, CONCRETE PLATFORM AND HANDRAIL |
3.06
| 1 | LS | $50,000.00 | $63,577.67 |
$63,577.67
| $117,671.61 | $129,790.50 |
| CATERPILLAR GATE SYSTEM REPAIR AND REFURBISHMENT |
8.08
| 1 | LS | $328,587.00 | $168,055.01 |
$168,055.01
| $206,343.84 | $205,300.00 |
| CHAIN LINK FENCE, 5' HIGH WITH BARBED WIRE |
0.28
| 10 | LF | $100.00 | $573.70 |
$5,737.00
| $378.78 | $278.50 |
| AUTOMATIC SWING GATE OPERATOR |
1.17
| 1 | LS | $25,000.00 | $24,224.89 |
$24,224.89
| $26,131.98 | $25,612.45 |
| 20" STEEL PIPE, PIPE FITTINGS, FLEX COUPLINGS, AND PIPE FLANGES |
5.80
| 1 | LS | $200,304.00 | $120,517.11 |
$120,517.11
| $184,134.19 | $179,444.00 |
| 20" BONNETED KNIFE GATE VALVES AND ELECTRIC ACTUATORS |
8.89
| 2 | EA | $152,884.00 | $92,390.30 |
$184,780.60
| $165,929.55 | $147,500.00 |
| 3" BYPASS LINE PIPE, FITTING, BALL VALVE, AND AIR VALVE |
1.37
| 1 | LS | $14,497.00 | $28,392.85 |
$28,392.85
| $16,538.48 | $17,119.00 |
| 16" PLUNGER VALVE AND ELECTRIC ACTUATOR |
12.58
| 1 | LS | $107,155.00 | $261,495.45 |
$261,495.45
| $261,344.58 | $284,333.73 |
| STRUCTURE CONCRETE (INCLUDING REINFORCEMENT) |
0.82
| 12 | CY | $2,000.00 | $1,418.18 |
$17,018.16
| $2,371.53 | $2,200.00 |
| Total Percent | 100 | | | | Total Amount | $2,079,111.44 | | |