Bid Price History

San Gabriel Coastal Spreading Grounds Levee Retrofit Project
$7,494,211.00
12/18/2018
676 (H4),676 (H6),676 (H5),676 (G6),676 (G7)
4
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.03 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.03 4MTH$500.00$500.00 $2,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $5,000) 0.07 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.004PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) 0.07 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.007IMPLEMENTATION OF THE SWPPP 0.53 1LS$51,500.00$40,000.00 $40,000.00 $51,718.75$32,500.00
001.08.005OFFICE FACILITIES 0.32 6MTH$3,090.00$4,000.00 $24,000.00 $4,125.00$4,250.00
001.09.003MOBILIZATION 9.07 1LS$560,235.83$680,000.00 $680,000.00 $557,500.00$550,000.00
300.01.003CLEARING AND GRUBBING 0.01 1LS$5,150.00$1,000.00 $1,000.00 $127,600.00$129,700.00
300.01.054RELOCATE EXISTING CHAIN LINK FENCE 0.21 1968LF$72.10$8.00 $15,744.00 $31.88$34.75
300.01.063AC PAVEMENT REMOVAL 1.03 77265SF$2.06$1.00 $77,265.00 $1.50$1.50
300.01.067CONCRETE REMOVAL (REINFORCED) 0.09 5CY$772.50$1,300.00 $6,500.00 $1,012.50$1,000.00
301.02.005CRUSHED MISCELLANEOUS BASE 0.90 844CY$51.50$80.00 $67,520.00 $81.06$87.13
302.05.013AC PAVEMENT 1.82 1365TON$154.50$100.00 $136,500.00 $135.00$132.50
302.06.003PCC PAVEMENT 0.12 5CY$1,030.00$1,800.00 $9,000.00 $1,350.00$1,300.00
 TEMPORARILY REMOVE AND REINSTALL ELECTRONIC GATE BETWEEN THE DESILTING BASIN AND BASIN 1 0.07 1LS$10,300.00$5,000.00 $5,000.00 $12,975.00$12,500.00
 STEEL PRESS-IN SHEET PILE CUT-OFF WALL 73.47 3012LF$2,060.00$1,828.00 $5,505,936.00 $2,139.50$2,115.00
 REPAIR CRACKS IN CONCRETE INTAKE FLUME 0.06 200LF$6.18$22.00 $4,400.00 $111.75$62.50
 REMOVE AND RESTORE AIR VENT (DETAILS 1 AND 2) 0.09 2EA$5,150.00$3,500.00 $7,000.00 $17,535.00$8,320.00
 REINFORCING GEOGRID 0.10 1033SY$5.15$7.00 $7,231.00 $13.00$10.00
 PRE- AND POST-CONSTRUCTION VIDEO INSPECTION 0.66 4100LF$10.30$12.00 $49,200.00 $10.50$10.00
 JOBS COORDINATOR 0.27 1LS$10,000.00$20,000.00 $20,000.00 $59,500.00$36,500.00
 JET GROUT TEST PROGRAM 0.83 1LS$154,500.00$62,100.00 $62,100.00 $107,450.00$81,050.00
 JET GROUT CUT-OFF WALL (UTILITY CROSSING 5) 1.90 25LF$7,210.00$5,700.00 $142,500.00 $5,392.50$5,700.00
 JET GROUT CUT-OFF WALL (UTILITY CROSSING 4) 2.20 30LF$7,210.00$5,500.00 $165,000.00 $5,332.50$5,600.00
 JET GROUT CUT-OFF WALL (UTILITY CROSSING 3) 1.94 26LF$7,210.00$5,600.00 $145,600.00 $5,365.00$5,650.00
 JET GROUT CUT-OFF WALL (UTILITY CROSSING 2) 1.63 21LF$7,210.00$5,800.00 $121,800.00 $5,428.75$5,750.00
 JET GROUT CUT-OFF WALL (UTILITY CROSSING 1) 2.32 29LF$7,210.00$6,000.00 $174,000.00 $5,460.00$5,850.00
 UNCLASSIFIED EXCAVATION (EQUIPMENT TRENCH) 0.17 287CY$8.46$45.00 $12,915.00 $106.75$72.50
 Total Percent100   Total Amount$7,494,211.00