Bid Price History

Marie Canyon Stormwater Disinfection System Upgrade
$1,646,300.00
11/26/2024
628 (G7)
4
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.15 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.15 5MTH$500.00$500.00 $2,500.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.06 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.67 1LS$30,000.00$11,069.00 $11,069.00 $14,517.25$13,034.50
001.07.003IMPLEMENTATION OF BMPS 1.34 1LS$5,000.00$22,137.00 $22,137.00 $18,284.25$19,500.00
001.07.023PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5000) 0.30 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.025IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 0.45 1LS$8,000.00$7,379.00 $7,379.00 $6,469.75$7,439.50
001.07.041IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND COLLECTION PLAN 0.67 1LS$20,000.00$11,069.00 $11,069.00 $9,267.25$8,034.50
001.08.005OFFICE FACILITIES 0.43 6MTH$7,000.00$1,181.00 $7,086.00 $3,170.25$3,500.00
001.09.003MOBILIZATION 1.43 1LS$80,000.00$23,613.00 $23,613.00 $157,153.25$99,500.00
601.09.011TRAFFIC CONTROL 1.79 1LS$85,000.00$29,517.00 $29,517.00 $80,654.25$67,258.50
 STRUCTURAL WALL 3.17 1LS$25,000.00$52,227.00 $52,227.00 $60,431.75$56,113.50
 SCREEN FILTERS 4.64 1LS$20,000.00$76,448.00 $76,448.00 $53,882.00$53,014.00
 SELF-PRIMING PUMP 2.14 1LS$17,000.00$35,184.00 $35,184.00 $47,546.00$47,500.00
 PREPARATION OF THE DEBRIS CONTAINMENT AND COLLECTION PLAN 0.22 1LS$3,000.00$3,690.00 $3,690.00 $5,547.50$5,595.00
 REMOVAL AND RECYCLING OF UNIVERSAL WASTE 0.40 1LS$3,000.00$6,641.00 $6,641.00 $16,910.25$8,320.50
 OPERATIONAL TESTS 0.67 1LS$11,500.00$11,069.00 $11,069.00 $17,767.25$15,534.50
 PREPARATION OF TEMPORARY BYPASS 0.31 1LS$3,600.00$5,165.00 $5,165.00 $7,291.25$7,582.50
 MECHANICAL DEMOLITION 5.01 1LS$20,000.00$82,499.00 $82,499.00 $65,887.25$66,249.50
 MISCELLANEOUS MECHANICAL WORK 4.05 1LS$22,600.00$66,707.00 $66,707.00 $172,759.25$137,165.00
 IMPLEMENTATION OF TEMPORARY BYPASS 1.65 1LS$22,500.00$27,095.00 $27,095.00 $51,309.75$50,000.00
 ELECTRICAL WORK 28.71 1LS$175,000.00$472,583.00 $472,583.00 $453,320.75$463,791.50
 FILTRATION SYSTEMS 36.94 1LS$365,200.00$608,064.00 $608,064.00 $663,859.75$619,219.50
 ULTRAVIOLET DISINFECTION SYSTEM 4.62 1LS$34,000.00$76,058.00 $76,058.00 $71,977.00$71,829.00
 Total Percent100   Total Amount$1,646,300.00