Bid Price History

Pine Canyon Road
$3,288,999.00
03/06/2018
4101 (E1),4101 (H2),4101 (H1),4101 (G1),4101 (F1)
7
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $1,000) 0.03 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.08 5MTH$500.00$500.00 $2,500.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.03 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.003IMPLEMENTATION OF BMPS 0.18 1LS$5,000.00$6,000.00 $6,000.00 $14,598.62$15,000.00
001.08.005OFFICE FACILITIES 0.61 5MTH$6,000.00$4,000.00 $20,000.00 $2,997.86$3,000.00
001.09.003MOBILIZATION 6.98 1LS$200,000.00$229,606.30 $229,606.30 $256,229.47$234,000.00
300.01.003CLEARING AND GRUBBING 0.15 1LS$20,000.00$5,000.00 $5,000.00 $54,000.00$30,000.00
300.02.003UNCLASSIFIED EXCAVATION 0.95 180CY$150.00$173.00 $31,140.00 $121.71$114.00
300.05.002IMPORTED BORROW 2.38 898CY$60.00$87.00 $78,126.00 $104.00$97.00
302.05.013AC PAVEMENT 1.21 358TON$150.00$111.00 $39,738.00 $156.57$140.00
302.05.017AC PAVEMENT(INVERTED SHOULDERS) 2.12 610TON$100.00$114.50 $69,845.00 $157.93$150.00
302.05.024ADJUST MANHOLE 0.27 2EA$800.00$4,500.00 $9,000.00 $2,857.14$2,000.00
302.09.003ASPHALT RUBBER HOT MIX 37.44 11772TON$100.00$104.60 $1,231,351.20 $108.92$108.00
302.09.005ASPHALT RUBBER HOT MIX (TEST STRIP) 1.92 500TON$110.00$126.60 $63,300.00 $124.35$126.60
302.15.003CIR AC PAVEMENT, 3" THICK 24.82 143216SY$8.00$5.70 $816,331.20 $5.98$6.00
302.15.007EMULSIFIED RECYCLING AGENT 10.43 550TON$700.00$624.00 $343,200.00 $637.43$633.00
312.01.017INSTALL FIRE HYDRANT LOCATION RPM 0.02 1EA$25.00$570.00 $570.00 $197.57$105.00
601.09.011TRAFFIC CONTROL 3.53 1LS$170,000.00$116,000.00 $116,000.00 $160,839.86$176,000.00
601.09.019CHANGEABLE MESSAGE SIGN 0.31 2EA$5,000.00$5,100.00 $10,200.00 $4,942.86$5,000.00
 AC PAVEMENT (OVERSIDE DRAINS) 0.29 21TON$300.00$457.00 $9,597.00 $735.29$500.00
 IMPORTED RECLAIMED ASPHALT PAVEMENT (RAP) 6.25 5049TON$23.00$40.70 $205,494.30 $36.39$39.00
 Total Percent100   Total Amount$3,288,999.00