| Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
| 001.06.002 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| 001.06.003 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.05
| 5 | MTH | $500.00 | $500.00 |
$2,500.00
| $500.00 | $500.00 |
| 001.06.007 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.02
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
| 001.06.011 | IMPLEMENTATION OF THE LTWHP |
0.59
| 1 | LS | $10,000.00 | $27,000.00 |
$27,000.00
| $44,892.86 | $35,000.00 |
| 001.07.021 | SHORING OF OPEN EXCAVATIONS |
8.03
| 1 | LS | $30,000.00 | $370,000.00 |
$370,000.00
| $277,857.14 | $300,000.00 |
| 001.08.005 | OFFICE FACILITIES |
0.65
| 6 | MTH | $8,000.00 | $5,000.00 |
$30,000.00
| $11,308.57 | $11,000.00 |
| 001.09.003 | MOBILIZATION |
8.68
| 1 | LS | $320,000.00 | $400,000.00 |
$400,000.00
| $563,101.71 | $600,000.00 |
| 300.01.003 | CLEARING AND GRUBBING |
0.87
| 1 | LS | $29,000.00 | $40,000.00 |
$40,000.00
| $135,571.43 | $59,000.00 |
| 300.04.007 | STRUCTURE EXCAVATION (BRIDGE) |
1.55
| 840 | CY | $130.00 | $85.00 |
$71,400.00
| $242.43 | $275.00 |
| 300.04.027 | STRUCTURE BACKFILL (BRIDGE) |
1.17
| 540 | CY | $250.00 | $100.00 |
$54,000.00
| $291.29 | $300.00 |
| 303.01.006 | STRUCTURE CONCRETE (BRIDGE) |
12.63
| 353 | CY | $2,200.00 | $1,650.00 |
$582,450.00
| $3,488.00 | $3,776.00 |
| 303.01.011 | STRUCTURE CONCRETE (FOOTING) |
4.18
| 175 | CY | $1,000.00 | $1,100.00 |
$192,500.00
| $1,434.43 | $1,311.00 |
| 303.01.042 | BAR REINFORCING STEEL (BRIDGE) |
9.32
| 171870 | LB | $3.20 | $2.50 |
$429,675.00
| $2.64 | $2.50 |
| 303.01.115 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) |
1.33
| 1225 | LF | $60.00 | $50.00 |
$61,250.00
| $90.86 | $95.00 |
| | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (GIRDER) |
0.23
| 350 | SF | $150.00 | $30.00 |
$10,500.00
| $262.29 | $182.00 |
| | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (BARRIER) |
0.08
| 75 | SF | $240.00 | $50.00 |
$3,750.00
| $178.43 | $182.00 |
| | REPAIR SPALLED CONCRETE (BARRIER) |
0.24
| 75 | SF | $240.00 | $150.00 |
$11,250.00
| $216.43 | $175.00 |
| | REPAIR SPALLED CONCRETE (GIRDER) |
0.46
| 350 | SF | $150.00 | $60.00 |
$21,000.00
| $223.57 | $175.00 |
| | REMOVAL OF ESA FENCING |
0.04
| 1 | LS | $2,500.00 | $2,000.00 |
$2,000.00
| $5,362.43 | $5,500.00 |
| | PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | PREPARATION OF THE WPCP (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | PREPARATION OF SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $5,000) |
0.11
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
| | PREPARATION OF THE DEWATERING PLAN (STIPULATED UNIT PRICE OF $5,000) |
0.11
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
| | PREPARATION OF THE MONITORING WELL DECOMMISSIONING PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | MICROPILES |
42.17
| 54 | EA | $12,500.00 | $36,000.00 |
$1,944,000.00
| $36,853.86 | $40,000.00 |
| | INSTALLATION OF ESA FENCING |
0.25
| 1650 | LF | $5.00 | $7.00 |
$11,550.00
| $11.10 | $10.00 |
| | MAINTENANCE OF ESA FENCING |
0.10
| 1650 | LF | $2.00 | $2.70 |
$4,455.00
| $6.11 | $3.00 |
| | IMPLEMENTATION OF THE DEWATERING PLAN |
2.69
| 1 | LS | $300,000.00 | $124,000.00 |
$124,000.00
| $480,048.57 | $400,000.00 |
| | IMPLEMENTATION OF THE MONITORING WELL DECOMMISSIONING PLAN |
0.41
| 2 | EA | $60,000.00 | $9,500.00 |
$19,000.00
| $28,024.29 | $20,000.00 |
| | IMPLEMENTATION OF THE WPCP |
1.13
| 1 | LS | $20,000.00 | $52,000.00 |
$52,000.00
| $148,207.14 | $60,000.00 |
| | IMPLEMENTATION OF SURFACE WATER DIVERSION PLAN |
1.63
| 1 | LS | $70,000.00 | $75,000.00 |
$75,000.00
| $168,308.57 | $123,160.00 |
| | CONSTRUCTION DEWATERING MONITORING AND REPORTING |
0.65
| 6 | MTH | $5,000.00 | $5,000.00 |
$30,000.00
| $5,081.29 | $5,000.00 |
| | UTILITY PROTECTION IN PLACE |
0.43
| 1 | LS | $30,000.00 | $20,000.00 |
$20,000.00
| $39,842.86 | $40,000.00 |
| | Total Percent | 100 | | | | Total Amount | $4,610,280.00 | | |