Bid Price History

Uncontrolled Marked Crosswalk Improvements
$706,775.00
12/18/2018
(-)
2
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
310.05.034PAVEMENT MARKINGS (THERMOPLASTIC) 9.28 13112SF$3.50$5.00 $65,560.00 $7.00$7.00
310.05.04024" STRIPING (THERMOPLASTIC) 6.80 4804LF$3.40$10.00 $48,040.00 $9.00$9.00
310.05.04012" STRIPING (THERMOPLASTIC) 0.32 450LF$4.40$5.00 $2,250.00 $4.95$4.95
310.05.043CURB MARKINGS (ONE-COAT PAINT) 0.64 300LF$2.50$15.00 $4,500.00 $11.50$11.50
310.05.129REMOVE PAVEMENT MARKINGS (THERMOPLASTIC) 9.03 12760SF$1.90$5.00 $63,800.00 $7.30$7.30
310.05.137REMOVE CURB MARKINGS (PAINT) 0.35 25SF$2.50$100.00 $2,500.00 $55.00$55.00
315.06.003SIGN PANEL 13.03 614EA$100.00$150.00 $92,100.00 $185.00$185.00
315.06.023RELOCATE SIGN 2.58 73EA$120.00$250.00 $18,250.00 $175.00$175.00
315.06.025REMOVE SIGN 4.34 307EA$30.00$100.00 $30,700.00 $62.50$62.50
 TRAFFIC CONTROL - SD2 20.37 1LS$85,000.00$144,000.00 $144,000.00 $113,400.00$113,400.00
 TRAFFIC CONTROL - SD1 13.02 1LS$50,000.00$92,000.00 $92,000.00 $69,000.00$69,000.00
 TRAFFIC CONTROL- SD5 6.23 1LS$50,000.00$44,000.00 $44,000.00 $37,000.00$37,000.00
 TRAFFIC CONTROL- SD4 4.53 1LS$15,000.00$32,000.00 $32,000.00 $26,000.00$26,000.00
 SIGN POST (ROADSIDE SIGN) 5.10 206EA$150.00$175.00 $36,050.00 $220.00$220.00
 REMOVE 12" STRIPING 0.40 565LF$4.25$5.00 $2,825.00 $4.50$4.50
 REMOVE 24" STRIPING 0.59 420LF$5.00$10.00 $4,200.00 $8.00$8.00
 REMOVE 4" STRIPING 0.16 75LF$2.50$15.00 $1,125.00 $10.00$10.00
 YIELD LINE (DETAIL "A") (THERMOPLASTIC) 3.24 4575SF$3.50$5.00 $22,875.00 $6.50$6.50
 Total Percent100   Total Amount$706,775.00