Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) |
0.08
| 0.50 | LS | $2,000.00 | $2,000.00 |
$1,000.00
| $2,000.00 | $2,000.00 |
001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.08
| 2 | MTH | $500.00 | $500.00 |
$1,000.00
| $500.00 | $500.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.04
| 0.50 | LS | $1,000.00 | $1,000.00 |
$500.00
| $1,000.00 | $1,000.00 |
001.06.011 | IMPLEMENTATION OF THE LTWHP |
0.38
| 0.50 | LS | $10,000.00 | $10,000.00 |
$5,000.00
| $14,500.00 | $10,000.00 |
001.07.003 | IMPLEMENTATION OF BMPS |
0.38
| 0.50 | LS | $6,000.00 | $10,000.00 |
$5,000.00
| $8,300.00 | $10,000.00 |
001.08.005 | OFFICE FACILITIES |
0.68
| 3 | MTH | $3,500.00 | $3,000.00 |
$9,000.00
| $3,360.00 | $3,000.00 |
001.09.003 | MOBILIZATION |
1.49
| 0.50 | LS | $146,000.00 | $39,490.66 |
$19,745.33
| $86,098.13 | $63,000.00 |
300.01.065 | CONCRETE REMOVAL (NON-REINFORCED) |
4.06
| 317 | CY | $300.00 | $170.00 |
$53,890.00
| $182.00 | $164.00 |
300.02.003 | UNCLASSIFIED EXCAVATION |
9.69
| 1288 | CY | $120.00 | $100.00 |
$128,800.00
| $113.80 | $100.00 |
300.03.003 | UNCLASSIFIED FILL |
1.91
| 422 | CY | $1.00 | $60.00 |
$25,320.00
| $99.80 | $82.00 |
301.02.005 | CRUSHED MISCELLANEOUS BASE |
2.52
| 508 | CY | $108.00 | $66.00 |
$33,528.00
| $124.40 | $130.00 |
302.01.005 | COLD MILL AC PAVEMENT (0 - 1-1/2") |
2.12
| 128232 | SF | $0.27 | $0.22 |
$28,211.04
| $0.23 | $0.22 |
302.01.007 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") |
6.39
| 292571 | SF | $0.37 | $0.29 |
$84,845.59
| $0.29 | $0.29 |
302.05.013 | AC PAVEMENT |
3.12
| 276 | TON | $129.00 | $150.00 |
$41,400.00
| $154.70 | $150.00 |
302.05.014 | AC PAVEMENT(PATCH BACK) |
0.12
| 5 | TON | $269.00 | $325.00 |
$1,625.00
| $645.00 | $500.00 |
302.05.015 | AC PAVEMENT(MEDIANS) |
1.17
| 104 | TON | $146.00 | $150.00 |
$15,600.00
| $181.60 | $165.00 |
302.05.019 | AC PAVEMENT(LEVELING COURSE) |
3.28
| 379 | TON | $111.00 | $115.00 |
$43,585.00
| $121.20 | $122.00 |
302.05.025 | DOUBLE ADJUST MANHOLE |
1.26
| 14 | EA | $2,000.00 | $1,200.00 |
$16,800.00
| $1,138.00 | $1,200.00 |
302.06.003 | PCC PAVEMENT |
2.68
| 79 | CY | $550.00 | $450.00 |
$35,550.00
| $517.80 | $500.00 |
302.09.003 | ASPHALT RUBBER HOT MIX |
31.18
| 4361 | TON | $132.00 | $95.00 |
$414,295.00
| $93.20 | $94.00 |
302.09.005 | ASPHALT RUBBER HOT MIX (TEST STRIP) |
3.57
| 500 | TON | $132.00 | $95.00 |
$47,500.00
| $103.60 | $99.00 |
303.05.016 | PCC CURB & GUTTER, TYPE A3-8 |
6.62
| 3141 | LF | $27.00 | $28.00 |
$87,948.00
| $32.80 | $30.00 |
303.05.043 | PCC WALK, 4" THICK |
0.12
| 132 | SF | $20.00 | $12.00 |
$1,584.00
| $15.00 | $16.00 |
303.05.050 | PCC CURB RAMPS |
0.28
| 5 | CY | $1,800.00 | $750.00 |
$3,750.00
| $945.00 | $975.00 |
303.05.059 | DETECTABLE WARNING SURFACE |
0.11
| 30 | SF | $65.00 | $50.00 |
$1,500.00
| $53.50 | $50.00 |
303.05.061 | CROSS GUTTER |
1.17
| 24 | CY | $500.00 | $650.00 |
$15,600.00
| $633.00 | $650.00 |
307.02.031 | 2-PAIR DETECTOR LEAD-IN CABLE |
0.24
| 320 | LF | $3.00 | $10.00 |
$3,200.00
| $7.31 | $7.00 |
310.05.007 | DETAIL 38 (THERMOPLASTIC) |
0.25
| 2427 | LF | $3.00 | $1.35 |
$3,276.45
| $1.10 | $1.10 |
310.05.007 | DETAIL 39 (THERMOPLASTIC) |
0.59
| 12713 | LF | $2.00 | $0.62 |
$7,882.06
| $0.78 | $0.70 |
310.05.007 | DETAIL 40 (THERMOPLASTIC) |
0.02
| 448 | LF | $1.50 | $0.65 |
$291.20
| $0.84 | $0.60 |
310.05.007 | DETAIL 29 (THERMOPLASTIC) |
0.06
| 580 | LF | $3.50 | $1.35 |
$783.00
| $1.30 | $1.25 |
310.05.007 | DETAIL 32 (THERMOPLASTIC) |
0.10
| 940 | LF | $3.00 | $1.35 |
$1,269.00
| $1.30 | $1.25 |
310.05.007 | DETAIL 22 (THERMOPLASTIC) |
0.10
| 1537 | LF | $2.00 | $0.90 |
$1,383.30
| $0.94 | $0.90 |
310.05.007 | DETAIL 26 (THERMOPLASTIC) |
0.09
| 2960 | LF | $1.50 | $0.40 |
$1,184.00
| $0.28 | $0.25 |
310.05.007 | DETAIL 2 (THERMOPLASTIC) |
0.09
| 2060 | LF | $1.50 | $0.55 |
$1,133.00
| $0.53 | $0.55 |
310.05.007 | DETAIL 9 (THERMOPLASTIC) |
0.30
| 7360 | LF | $1.50 | $0.55 |
$4,048.00
| $0.53 | $0.55 |
310.05.014 | DETAIL 39A (THERMOPLASTIC) |
0.26
| 6255 | LF | $2.00 | $0.55 |
$3,440.25
| $0.61 | $0.60 |
310.05.034 | PAVEMENT MARKINGS (THERMOPLASTIC) |
1.88
| 7570 | SF | $7.00 | $3.30 |
$24,981.00
| $4.53 | $5.00 |
310.05.040 | 12" STRIPING (THERMOPLASTIC) |
0.15
| 875 | LF | $4.00 | $2.25 |
$1,968.75
| $2.89 | $3.00 |
310.05.040 | 4" STRIPING (THERMOPLASTIC) |
0.09
| 2159 | LF | $2.00 | $0.55 |
$1,187.45
| $0.54 | $0.55 |
310.05.040 | 6" STRIPING (THERMOPLASTIC) |
0.04
| 808 | LF | $2.00 | $0.65 |
$525.20
| $0.82 | $0.80 |
310.05.043 | CURB MARKINGS (ONE-COAT PAINT) |
0.11
| 1163 | LF | $3.00 | $1.30 |
$1,511.90
| $1.55 | $1.30 |
310.05.106 | REMOVE DETAIL 9 (THERMOPLASTIC) |
0.09
| 1200 | LF | $1.50 | $1.00 |
$1,200.00
| $1.37 | $1.00 |
310.05.106 | REMOVE DETAIL 38 (THERMOPLASTIC) |
0.15
| 1285 | LF | $2.00 | $1.55 |
$1,991.75
| $2.37 | $2.00 |
310.05.106 | REMOVE DETAIL 22 (THERMOPLASTIC) |
0.05
| 452 | LF | $2.00 | $1.55 |
$700.60
| $2.05 | $2.00 |
310.05.106 | REMOVE DETAIL 29 (THERMOPLASTIC) |
0.06
| 195 | LF | $2.00 | $4.00 |
$780.00
| $2.82 | $2.80 |
310.05.129 | REMOVE PAVEMENT MARKINGS (THERMOPLASTIC) |
0.27
| 1518 | SF | $4.00 | $2.35 |
$3,567.30
| $2.41 | $2.35 |
310.05.135 | REMOVE 4" STRIPING (THERMOPLASTIC) |
0.05
| 570 | LF | $2.00 | $1.15 |
$655.50
| $1.45 | $1.15 |
310.05.135 | REMOVE 12" STRIPING (THERMOPLASTIC) |
0.02
| 50 | LF | $3.00 | $4.00 |
$200.00
| $2.63 | $2.35 |
310.05.137 | REMOVE CURB MARKINGS (PAINT) |
0.11
| 266 | SF | $2.00 | $5.50 |
$1,463.00
| $7.24 | $7.00 |
312.01.017 | INSTALL FIRE HYDRANT LOCATION RPM |
0.04
| 28 | EA | $40.00 | $20.00 |
$560.00
| $17.90 | $20.00 |
315.06.003 | SIGN PANEL |
0.89
| 91 | EA | $200.00 | $130.00 |
$11,830.00
| $111.90 | $115.00 |
315.06.025 | REMOVE SIGN |
0.05
| 15 | EA | $100.00 | $40.00 |
$600.00
| $52.90 | $52.50 |
315.06.029 | REMOVE SIGN POST |
0.10
| 9 | EA | $250.00 | $155.00 |
$1,395.00
| $86.80 | $53.00 |
601.09.011 | TRAFFIC CONTROL |
2.26
| 0.50 | LS | $110,000.00 | $60,000.00 |
$30,000.00
| $100,878.32 | $77,400.00 |
601.09.017 | FLASHING ARROW SIGN |
0.78
| 8 | EA | $5,000.00 | $1,300.00 |
$10,400.00
| $2,300.00 | $1,500.00 |
| WHEEL STOP REMOVAL |
0.05
| 12 | EA | $150.00 | $50.00 |
$600.00
| $47.20 | $42.00 |
| SIGN POST (ROADSIDE SIGN) |
0.67
| 35 | EA | $350.00 | $255.00 |
$8,925.00
| $220.00 | $250.00 |
| SIGNAL HEADS (3-12" LED VEHICLE HEAD) |
0.75
| 9 | EA | $1,200.00 | $1,100.00 |
$9,900.00
| $1,120.00 | $1,100.00 |
| INDUCTIVE LOOP DETECTOR AND LEAD SAW CUT |
3.08
| 4098 | LF | $12.30 | $10.00 |
$40,980.00
| $11.45 | $11.00 |
| 2" PVC CONDUIT |
1.08
| 221 | LF | $45.00 | $65.00 |
$14,365.00
| $60.05 | $63.00 |
| NEW TENON ON EXST SIGNAL MAST ARM |
0.60
| 2 | EA | $600.00 | $4,000.00 |
$8,000.00
| $4,050.00 | $4,000.00 |
| Total Percent | 100 | | | | Total Amount | $1,328,754.67 | | |