Chesebro Road over Chesebro Canyon Creek Bridge 854 On-System (2018WOOLSEYFIRE)
$708,000.00
12/13/2018
558 (D5)
1
* Non-standard items are shaded yellow
Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.09.003 | MOBILIZATION |
7.49
| 1 | LS | $53,000.00 | $53,000.00 |
$53,000.00
| $53,000.00 | $53,000.00 |
| FURNISH & INSTALL BRIDGE (INCLUDES ENGINEERING) |
46.75
| 1 | LS | $331,000.00 | $331,000.00 |
$331,000.00
| $331,000.00 | $331,000.00 |
| FURNISH & INSTALL BRIDGE ABUTMENTS |
4.24
| 1 | LS | $30,000.00 | $30,000.00 |
$30,000.00
| $30,000.00 | $30,000.00 |
| FURNISH & INSTALL CANTILEVER RETAINING WALLS |
25.99
| 1 | LS | $184,000.00 | $184,000.00 |
$184,000.00
| $184,000.00 | $184,000.00 |
| METAL RAIL |
8.47
| 1 | LS | $60,000.00 | $60,000.00 |
$60,000.00
| $60,000.00 | $60,000.00 |
| AC PAVING |
2.82
| 1 | LS | $20,000.00 | $20,000.00 |
$20,000.00
| $20,000.00 | $20,000.00 |
| REMOVALS & DISPOSAL |
4.24
| 1 | LS | $30,000.00 | $30,000.00 |
$30,000.00
| $30,000.00 | $30,000.00 |
| Total Percent | 100 | | | | Total Amount | $708,000.00 | | |