Bid Price History

Chesebro Road over Chesebro Canyon Creek Bridge 854 On-System (2018WOOLSEYFIRE)
$708,000.00
12/13/2018
558 (D5)
1
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.09.003MOBILIZATION 7.49 1LS$53,000.00$53,000.00 $53,000.00 $53,000.00$53,000.00
 FURNISH & INSTALL BRIDGE (INCLUDES ENGINEERING) 46.75 1LS$331,000.00$331,000.00 $331,000.00 $331,000.00$331,000.00
 FURNISH & INSTALL BRIDGE ABUTMENTS 4.24 1LS$30,000.00$30,000.00 $30,000.00 $30,000.00$30,000.00
 FURNISH & INSTALL CANTILEVER RETAINING WALLS 25.99 1LS$184,000.00$184,000.00 $184,000.00 $184,000.00$184,000.00
 METAL RAIL 8.47 1LS$60,000.00$60,000.00 $60,000.00 $60,000.00$60,000.00
 AC PAVING 2.82 1LS$20,000.00$20,000.00 $20,000.00 $20,000.00$20,000.00
 REMOVALS & DISPOSAL 4.24 1LS$30,000.00$30,000.00 $30,000.00 $30,000.00$30,000.00
 Total Percent100   Total Amount$708,000.00