Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.07.003 | IMPLEMENTATION OF BMPS |
0.93
| 1 | LS | $10,000.00 | $6,150.00 |
$6,150.00
| $6,150.00 | $6,150.00 |
001.09.003 | MOBILIZATION |
1.97
| 1 | LS | $50,000.00 | $13,000.00 |
$13,000.00
| $13,000.00 | $13,000.00 |
300.01.003 | CLEARING AND GRUBBING |
1.51
| 1 | LS | $5,000.00 | $10,000.00 |
$10,000.00
| $10,000.00 | $10,000.00 |
300.02.003 | UNCLASSIFIED EXCAVATION |
2.44
| 21 | CY | $137.50 | $766.50 |
$16,096.50
| $766.50 | $766.50 |
302.05.013 | AC PAVEMENT |
5.46
| 19 | TON | $412.50 | $1,900.50 |
$36,109.50
| $1,900.50 | $1,900.50 |
304.06.003 | REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) |
5.37
| 2491 | LF | $8.00 | $14.25 |
$35,496.75
| $14.25 | $14.25 |
304.06.009 | TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE |
3.13
| 41442 | LB | $0.25 | $0.50 |
$20,721.00
| $0.50 | $0.50 |
304.06.019 | MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) |
18.02
| 1883 | LF | $71.50 | $63.25 |
$119,099.75
| $63.25 | $63.25 |
304.06.043 | MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY (TYPE SFT) PER STD PLAN A77S1 |
0.11
| 1 | EA | $1,430.00 | $703.00 |
$703.00
| $703.00 | $703.00 |
304.06.047 | MIDWEST GUARDRAIL SYSTEM BURIED POST END ANCHOR PER STD PLAN A77T2 |
0.70
| 3 | EA | $2,090.00 | $1,548.00 |
$4,644.00
| $1,548.00 | $1,548.00 |
304.06.051 | TRANSITION RAILING (TYPE WB) |
4.09
| 5 | EA | $4,950.00 | $5,406.00 |
$27,030.00
| $5,406.00 | $5,406.00 |
601.09.011 | TRAFFIC CONTROL |
16.42
| 1 | LS | $70,000.00 | $108,526.00 |
$108,526.00
| $108,526.00 | $108,526.00 |
| IN-LINE TERMINAL SYSTEM (TYPE MSKT-SP-MGS) |
13.45
| 21 | EA | $8,580.00 | $4,233.00 |
$88,893.00
| $4,233.00 | $4,233.00 |
| SAWCUT & REMOVE INTERFERING PORTION OF ROCK |
1.29
| 1 | LS | $11,000.00 | $8,500.00 |
$8,500.00
| $8,500.00 | $8,500.00 |
| RURAL CB (MODIFIED) |
2.81
| 2 | EA | $5,500.00 | $9,296.00 |
$18,592.00
| $9,296.00 | $9,296.00 |
| SHOULDER GRADING |
5.50
| 2876 | LF | $1.67 | $12.65 |
$36,381.40
| $12.65 | $12.65 |
| CONCRETE BARRIER (TYPE 732 MODIFIED) |
3.69
| 20 | LF | $440.00 | $1,218.00 |
$24,360.00
| $1,218.00 | $1,218.00 |
| REMOVE & DISPOSE EXISTING BOLLARD |
0.15
| 3 | EA | $165.00 | $339.00 |
$1,017.00
| $339.00 | $339.00 |
| DELINEATOR PER CALTRANS STD PLAN A73C, CLASS 1, TYPE F |
0.27
| 92 | EA | $20.50 | $19.06 |
$1,753.52
| $19.06 | $19.06 |
| AC DIKE PER CALTRANS STD PLAN A87B |
1.84
| 644 | LF | $10.00 | $18.90 |
$12,171.60
| $18.90 | $18.90 |
| EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $ ) |
1.51
| 10000 | AL | $1.00 | $1.00 |
$10,000.00
| $1.00 | $1.00 |
| CRASH CUSHION |
9.34
| 1 | LS | $60,500.00 | $61,769.00 |
$61,769.00
| $61,769.00 | $61,769.00 |
| Total Percent | 100 | | | | Total Amount | $661,014.02 | | |