Bid Price History

Ladera Park Stormwater Improvements
$4,944,878.98
11/27/2018
673 (B5),673 (B6)
6
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.04 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.06 6MTH$500.00$500.00 $3,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.02 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.003IMPLEMENTATION OF BMPS 0.34 1LS$15,000.00$16,964.00 $16,964.00 $44,910.67$40,000.00
001.07.009RESTORATION OF EXISTING IMPROVEMENTS 0.44 1LS$13,000.00$21,590.00 $21,590.00 $68,598.33$45,000.00
001.07.021SHORING OF OPEN EXCAVATIONS 1.73 1LS$100,000.00$85,592.00 $85,592.00 $293,882.50$263,851.50
001.08.005OFFICE FACILITIES 0.41 6MTH$2,500.00$3,392.83 $20,356.98 $5,907.14$3,446.42
001.09.003MOBILIZATION 6.76 1LS$200,000.00$334,207.00 $334,207.00 $428,534.50$393,500.00
306.01.503RESTORATION OF PERMANENT SURFACING 2.89 1LS$85,000.00$143,140.00 $143,140.00 $117,190.00$146,570.00
601.09.011TRAFFIC CONTROL 1.37 1LS$100,000.00$67,500.00 $67,500.00 $52,833.33$37,500.00
 PRE-TREATMENT DEVICE 2.56 1LS$131,800.00$126,565.00 $126,565.00 $196,810.83$161,550.00
 SUBMERSIBLE LEVEL TRANSMITTERS AND APPURTENANCES 0.05 1LS$16,000.00$2,267.00 $2,267.00 $30,444.50$35,000.00
 TEMPORARY SOUND BARRIER 0.48 1LS$7,500.00$23,750.00 $23,750.00 $41,125.00$46,500.00
 WATER HARVESTING SYSTEM 5.85 1LS$229,500.00$289,066.00 $289,066.00 $290,177.67$269,533.00
 OPERATIONAL TESTS 1 1LS$15,000.00$49,350.00 $49,350.00 $36,258.33$27,500.00
 MISCELLANEOUS MECHANICAL WORK 1.43 1LS$20,000.00$70,941.00 $70,941.00 $74,624.72$72,970.50
 LANDSCAPING AND IRRIGATION 4.56 1LS$464,019.00$225,731.00 $225,731.00 $413,675.17$356,010.00
 JOBS COORDINATOR 0.23 1LS$20,000.00$11,566.00 $11,566.00 $29,327.67$22,500.00
 FLOW METER SENSORS 0.05 1LS$45,600.00$2,467.00 $2,467.00 $29,361.17$27,500.00
 ELECTRIC MOTOR OPERATOR AND APPURTENANCES 0.62 1LS$27,300.00$30,905.00 $30,905.00 $31,117.50$27,900.00
 ELECTRICAL WORK 8.93 1LS$308,689.00$441,495.00 $441,495.00 $501,131.33$455,074.00
 DRAINAGE 22.21 1LS$763,302.00$1,098,259.00 $1,098,259.00 $1,015,536.37$1,045,267.00
 DRYWELLS 37.22 1LS$3,001,330.00$1,840,572.00 $1,840,572.00 $2,323,075.33$2,157,460.00
 CAST IRON SLIDE GATE ASSEMBLY 0.69 1LS$41,000.00$33,928.00 $33,928.00 $52,621.33$47,500.00
 WATER QUALITY MONITORING INSTRUMENTATION 0.05 1LS$48,600.00$2,667.00 $2,667.00 $56,511.17$49,000.00
 Total Percent100   Total Amount$4,944,878.98