Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $1,000) 0.24 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.24 2MTH$500.00$500.00 $1,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.24 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.003IMPLEMENTATION OF BMPS 0.60 1LS$10,000.00$2,500.00 $2,500.00 $7,339.72$4,600.00
300.01.003CLEARING AND GRUBBING 11.75 1LS$5,000.00$49,000.00 $49,000.00 $14,746.67$5,100.00
300.01.065CONCRETE REMOVAL (NON-REINFORCED) 0.22 6CY$500.00$150.00 $900.00 $299.06$320.00
300.02.003UNCLASSIFIED EXCAVATION 19.25 892CY$89.00$90.00 $80,280.00 $70.11$70.00
301.02.005CRUSHED MISCELLANEOUS BASE 7.41 309CY$117.00$100.00 $30,900.00 $101.42$90.00
301.03.005TRENCH BACKFILL SLURRY (CLASS 270-E-500) 1.37 19CY$350.00$300.00 $5,700.00 $409.41$300.00
302.05.007AC CURB, TYPE D1-6 1.30 299LF$20.00$18.15 $5,426.85 $40.05$30.00
302.05.008AC CURB, TYPE D1-8 0.25 57LF$25.00$18.50 $1,054.50 $54.20$38.00
302.05.013AC PAVEMENT 21.17 534TON$129.00$165.37 $88,307.58 $169.48$165.37
302.05.014AC PAVEMENT(PATCH BACK) 3.67 51TON$200.00$300.00 $15,300.00 $271.89$260.00
302.05.017AC PAVEMENT(INVERTED SHOULDERS) 1.37 19TON$200.00$300.00 $5,700.00 $284.96$260.00
302.06.003PCC PAVEMENT 8.20 120CY$328.00$285.00 $34,200.00 $466.54$400.00
303.05.003PCC CURB, TYPE A1-6 0.37 62LF$30.00$25.00 $1,550.00 $44.14$40.00
303.05.004PCC CURB, TYPE A1-8 0.15 22LF$35.00$28.00 $616.00 $48.81$42.00
303.05.009PCC CURB & GUTTER, TYPE A2-6 2.24 246LF$25.00$38.00 $9,348.00 $48.00$45.00
303.05.010PCC CURB & GUTTER, TYPE A2-8 3.47 362LF$25.00$40.00 $14,480.00 $50.00$46.00
303.05.011PCC CURB & GUTTER, TYPE A2-VAR 0.56 56LF$30.00$42.00 $2,352.00 $50.00$46.00
303.05.041LONGITUDINAL GUTTER 2.30 24CY$300.00$400.00 $9,600.00 $499.57$452.15
303.05.047PCC WALK & DRIVEWAYS, 4" THICK 5.65 5890SF$6.00$4.00 $23,560.00 $7.11$6.87
303.05.050PCC CURB RAMPS 1.68 7CY$400.00$1,000.00 $7,000.00 $1,455.24$1,000.00
303.05.059DETECTABLE WARNING SURFACE 0.65 45SF$40.00$60.00 $2,700.00 $69.35$45.00
310.05.022DETAIL 27B (THERMOPLASTIC) 0.80 2391LF$1.50$1.40 $3,347.40 $2.44$1.51
310.05.034PAVEMENT MARKINGS (THERMOPLASTIC) 0.12 44SF$6.00$11.00 $484.00 $10.61$11.00
310.05.0408" STRIPING (THERMOPLASTIC) 0.04 86LF$4.00$1.90 $163.40 $3.88$3.00
310.05.04012" STRIPING (THERMOPLASTIC) 0.22 238LF$4.00$3.85 $916.30 $6.20$5.50
310.05.04024" STRIPING (THERMOPLASTIC) 0.14 78LF$7.00$7.70 $600.60 $10.59$10.70
310.05.043CURB MARKINGS (ONE-COAT PAINT) 1.13 1225LF$6.00$3.85 $4,716.25 $3.78$3.85
310.05.118REMOVE DETAIL 27B (THERMOPLASTIC) 0.18 340LF$4.00$2.20 $748.00 $3.45$3.00
310.05.129REMOVE PAVEMENT MARKINGS (THERMOPLASTIC) 0.01 22SF$5.00$2.75 $60.50 $5.65$5.35
310.05.135REMOVE 24" STRIPING (THERMOPLASTIC) 0.12 91LF$6.00$5.50 $500.50 $9.52$10.00
310.05.135REMOVE 12" STRIPING (THERMOPLASTIC) 0.15 235LF$5.00$2.75 $646.25 $5.65$5.35
315.06.003SIGN PANEL 0.30 9EA$150.00$137.50 $1,237.50 $195.90$150.00
315.06.005FURNISH ONE-POST (ROADSIDE SIGN) 0.08 3EA$100.00$110.00 $330.00 $137.28$115.00
315.06.015INSTALL ONE-POST (ROADSIDE SIGN) 0.06 3EA$100.00$82.50 $247.50 $165.04$150.00
315.06.017INSTALL SIGN (STRAP AND SADDLE BRACKET) 0.18 9EA$100.00$82.50 $742.50 $144.54$138.00
315.06.023RELOCATE SIGN 0.04 1EA$200.00$165.00 $165.00 $234.64$225.00
315.06.029REMOVE SIGN POST 0.01 1EA$150.00$55.00 $55.00 $141.92$97.00
601.09.011TRAFFIC CONTROL 0.96 1LS$20,000.00$4,000.00 $4,000.00 $22,981.94$13,000.00
 GRADE FLOWLINE 0.79 480LF$10.00$6.88 $3,302.40 $17.30$20.00
 ADJUST CHAIN LINK GATE 0.29 1LS$2,000.00$1,200.00 $1,200.00 $2,706.22$1,500.00
 FURNISH AND INSTALL CLASS 1 DELINEATORS (FLEXIBLE POST) 0.04 3EA$100.00$55.00 $165.00 $124.92$100.00
 Total Percent100   Total Amount$417,103.03