Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $3,000) |
0.27
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.14
| 3 | MTH | $500.00 | $500.00 |
$1,500.00
| $500.00 | $500.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.09
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
001.06.011 | IMPLEMENTATION OF THE LTWHP |
1.09
| 1 | LS | $10,000.00 | $12,000.00 |
$12,000.00
| $17,000.00 | $12,000.00 |
001.07.003 | IMPLEMENTATION OF BMPS |
1.36
| 1 | LS | $10,000.00 | $15,000.00 |
$15,000.00
| $13,225.00 | $12,675.00 |
001.07.021 | SHORING OF OPEN EXCAVATIONS |
4.98
| 1 | LS | $10,000.00 | $55,000.00 |
$55,000.00
| $36,291.67 | $36,000.00 |
001.08.005 | OFFICE FACILITIES |
0.54
| 3 | MTH | $4,000.00 | $2,000.00 |
$6,000.00
| $4,062.33 | $5,037.00 |
001.09.003 | MOBILIZATION |
5.89
| 1 | LS | $75,000.00 | $65,000.00 |
$65,000.00
| $142,913.33 | $65,000.00 |
300.02.003 | UNCLASSIFIED EXCAVATION |
1.10
| 173 | CY | $65.00 | $70.00 |
$12,110.00
| $83.00 | $70.00 |
302.01.007 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") |
3.18
| 2929 | SF | $0.70 | $12.00 |
$35,148.00
| $6.52 | $6.00 |
302.13.003 | PMAC PAVEMENT |
0.98
| 27 | TON | $250.00 | $400.00 |
$10,800.00
| $499.00 | $496.00 |
306.01.115 | 6" HIGH DENSITY POLYETHYLENE PIPE |
1.47
| 65 | LF | $200.00 | $250.00 |
$16,250.00
| $293.33 | $275.00 |
306.01.221 | AIR RELEASE AND VACUUM VALVE ASSEMBLY, 2" |
0.45
| 1 | EA | $8,000.00 | $5,000.00 |
$5,000.00
| $5,996.33 | $5,000.00 |
306.01.225 | BUTTERFLY VALVE, 150 PSI WWP, 30" |
2.17
| 1 | EA | $15,000.00 | $24,000.00 |
$24,000.00
| $22,754.67 | $22,425.00 |
306.01.227 | GATE VALVE, 200 PSI WWP, 12" |
2.90
| 4 | EA | $4,000.00 | $8,000.00 |
$32,000.00
| $4,683.33 | $4,425.00 |
500.00.015 | VIDEO INSPECTION |
0.32
| 1 | LS | $10,000.00 | $3,500.00 |
$3,500.00
| $4,333.33 | $3,500.00 |
601.09.011 | TRAFFIC CONTROL |
3.62
| 1 | LS | $30,000.00 | $40,000.00 |
$40,000.00
| $28,791.67 | $35,000.00 |
601.09.017 | FLASHING ARROW SIGN |
0.68
| 1 | EA | $5,000.00 | $7,500.00 |
$7,500.00
| $5,775.00 | $6,250.00 |
601.09.019 | CHANGEABLE MESSAGE SIGN |
0.45
| 1 | EA | $5,000.00 | $5,000.00 |
$5,000.00
| $5,483.33 | $5,200.00 |
900.02.003 | PUMP WELL ASSEMBLY, SIDE DRAINING, STD PLAN W-53, STYLE B |
1.36
| 1 | EA | $9,000.00 | $15,000.00 |
$15,000.00
| $12,443.33 | $14,300.00 |
900.02.025 | BARRICADE POSTS, STD PLAN W-14 |
1.09
| 16 | EA | $700.00 | $750.00 |
$12,000.00
| $1,361.67 | $1,060.00 |
| 8" PRESSURE REDUCING/SUSTAINING VALVE |
1.68
| 1 | EA | $11,000.00 | $18,500.00 |
$18,500.00
| $21,637.33 | $18,500.00 |
| 8" WATERMAIN, .25" THICK STL, CML & EPOXY COATED |
1.09
| 40 | LF | $300.00 | $300.00 |
$12,000.00
| $436.67 | $300.00 |
| 30" WATERMAIN, .25" THICK, STL, CML & CMC, WELDED |
2.17
| 40 | LF | $600.00 | $600.00 |
$24,000.00
| $655.00 | $600.00 |
| REINFORCED POLYETHYLENE GEOMEMBRANE |
5.98
| 26400 | SF | $0.55 | $2.50 |
$66,000.00
| $1.80 | $1.50 |
| REMOVE AND REINSTALL EXISTING CHAIN LINK FENCE |
1.63
| 60 | LF | $80.00 | $300.00 |
$18,000.00
| $226.00 | $243.00 |
| 12" WATERMAIN, .25" THICK STL, CML & CMC, WELDED |
18.57
| 547 | LF | $400.00 | $375.00 |
$205,125.00
| $443.00 | $390.00 |
| SAMPLING STATION |
0.45
| 1 | EA | $6,000.00 | $5,000.00 |
$5,000.00
| $5,438.00 | $5,464.00 |
| SAFETY SHOWER/EYEWASH |
0.91
| 1 | EA | $5,500.00 | $10,000.00 |
$10,000.00
| $6,679.00 | $5,037.00 |
| STRUCTURE CONCRETE (VESSEL FOUNDATION) |
7.10
| 98 | CY | $500.00 | $800.00 |
$78,400.00
| $858.00 | $800.00 |
| STRUCTURE CONCRETE (FOUNDATION) |
1.69
| 22 | CY | $500.00 | $850.00 |
$18,700.00
| $874.33 | $850.00 |
| STRUCTURE CONCRETE (BACKWASH TANK RINGWALL FOUNDATION) |
3.62
| 25 | CY | $800.00 | $1,600.00 |
$40,000.00
| $1,523.00 | $1,600.00 |
| TRENCH BACKFILL SLURRY (CLASS 140-S-100) |
0.62
| 57 | CY | $200.00 | $120.00 |
$6,840.00
| $339.00 | $350.00 |
| INTERCONNECTION TO EXISTING WATERMAIN |
4.07
| 3 | EA | $15,000.00 | $15,000.00 |
$45,000.00
| $22,065.33 | $17,875.00 |
| INTERCONNECTION TO EXISTING SEWER |
0.45
| 1 | EA | $10,000.00 | $5,000.00 |
$5,000.00
| $5,863.67 | $5,000.00 |
| 8" REDUCED PRESSURE PRINCIPLE ASSEMBLY |
1.63
| 1 | EA | $20,480.00 | $18,000.00 |
$18,000.00
| $24,766.67 | $27,300.00 |
| 36" X 36" DRAIN INLET |
0.54
| 1 | EA | $10,000.00 | $6,000.00 |
$6,000.00
| $8,175.00 | $8,775.00 |
| EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $5,000) |
0.45
| 5000 | AL | $1.00 | $1.00 |
$5,000.00
| $1.00 | $1.00 |
| CATHODIC PROTECTION ANODE AND TEST STATION |
0.54
| 1 | EA | $5,500.00 | $6,000.00 |
$6,000.00
| $7,266.67 | $6,000.00 |
| ELECTRICAL WORK |
12.68
| 1 | LS | $110,000.00 | $140,000.00 |
$140,000.00
| $135,066.67 | $135,200.00 |
| Total Percent | 100 | | | | Total Amount | $1,104,373.00 | | |