| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) | 10.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.10
| 0.00 | 0.10 | $20,000.00 | $2,000.00 |
| 6 | OFFICE FACILITIES | 10.00 | MTH |
1.00
| 0.00 | 1.00 | $1,500.00 | $1,500.00 |
| 8 | S-101 LOW PROFILE BARRICADES PHASE 1 | 2,836.00 | LF |
2,420.00
| 0.00 | 2,420.00 | $22.00 | $53,240.00 |
| 11 | S-101 GATE GUARDS / FLAG PERSONS | 190.00 | DAYS |
5.00
| 0.00 | 5.00 | $475.00 | $2,375.00 |
| 12 | P-101 ASPHALT CONCRETE PAVEMENT REMOVAL | 120,654.00 | SY |
50,000.00
| 0.00 | 50,000.00 | $1.59 | $79,500.00 |
| 13 | P-101 CONCRETE PAVEMENT REMOVAL | 90.00 | SY |
88.90
| 0.00 | 88.90 | $24.00 | $2,133.60 |
| 14 | P-101 TIE-DOWN ANCHOR REMOVAL | 1,107.00 | EA |
800.00
| 0.00 | 800.00 | $40.00 | $32,000.00 |