Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Puddingstone and Marshall Canyon Channels Trench Settlement Repair
Contractor: M K Construction
1040 W. HOOVER AVE
ORANGE, CA 92867
Project ID: FCC0001267
Federal Number(s): None
Original Contract: $326,025.00
Awarded: 7/11/2017
Period Ending: 12/21/2017
Board Accepted: 3/22/2018
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF BMPS1.00LS 0.90 0.000.90$20,000.00$18,000.00
6TREE REMOVAL (25"+ DIAMETER)2.00EA 2.00 0.002.00$1,100.00$2,200.00
7CROWN REDUCTION, TREE (25" + DIAMETER)3.00EA 1.00 0.001.00$1,300.00$1,300.00
8CONCRETE REMOVAL (NON-REINFORCED)52.00CY 52.00 0.0052.00$177.00$9,204.00
9UNCLASSIFIED EXCAVATION880.00CY 880.00 0.00880.00$64.00$56,320.00
10CRUSHED MISCELLANEOUS BASE586.00CY 586.00 0.00586.00$40.00$23,440.00
11AC PAVEMENT530.00TON 530.00 0.00530.00$97.00$51,410.00
12PCC CURB & GUTTER, TYPE A2-8440.00LF 414.00 0.00414.00$25.60$10,598.40
13PCC CURB & GUTTER, TYPE A3-8440.00LF 440.00 0.00440.00$25.60$11,264.00
14PCC WALK, 4" THICK240.00SF 240.00 0.00240.00$12.00$2,880.00
16TRAFFIC CONTROL1.00LS 1.00 0.001.00$61,083.00$61,083.00
17TEMPORARY CRASH CUSHION ARRAY3.00EA 3.00 0.003.00$1,200.00$3,600.00
18TEMPORARY RAILING (TYPE K)1,160.00LF 800.00 0.00800.00$30.00$24,000.00
19FLASHING ARROW SIGN4.00EA 4.00 0.004.00$600.00$2,400.00
20CHANGEABLE MESSAGE SIGN2.00EA 2.00 0.002.00$1,200.00$2,400.00
21LOCAL DEPRESSION PER STD PLAN 313, CASE E, & DETAIL "A"1.00EA 1.00 0.001.00$2,600.00$2,600.00
22LOCAL DEPRESSION PER STD PLAN 313, CASE E, & DETAIL "B"1.00EA 1.00 0.001.00$2,600.00$2,600.00
23MULTI-AXIAL GEOGRID3,600.00SY 3,560.00 0.003,560.00$5.35$19,046.00
S-1REGRADE BASE LS 1.00 0.001.00$1,880.00$1,880.00
S-2REMOVE THICKER ASPHALT SECTION LS 1.00 0.001.00$10,500.00$10,500.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
SCHEDULE UPDATEMONTHLY 1.00 0.001.00$250.00 $250.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $316,725.40 $0.00 $316,725.40
Retained $15,836.27 $0.00 $15,836.27
Deducted $250.00 $0.00 $250.00
Due $300,639.13 $0.00 $300,639.13