| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) | 10.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.20
| 0.10 | 0.10 | $20,000.00 | $2,000.00 |
| 6 | OFFICE FACILITIES | 10.00 | MTH |
2.00
| 1.00 | 1.00 | $1,500.00 | $1,500.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $375,000.00 | $187,500.00 |
| 11 | S-101 GATE GUARDS / FLAG PERSONS | 190.00 | DAYS |
10.00
| 5.00 | 5.00 | $475.00 | $2,375.00 |
| 12 | P-101 ASPHALT CONCRETE PAVEMENT REMOVAL | 120,654.00 | SY |
60,000.00
| 50,000.00 | 10,000.00 | $1.59 | $15,900.00 |
| 16 | P-101 SAWCUT AC PAVEMENT | 6,702.00 | LF |
1,000.00
| 0.00 | 1,000.00 | $2.50 | $2,500.00 |
| 29 | P-151 CLEARING AND GRUBBING | 1,640.00 | SY |
820.00
| 0.00 | 820.00 | $8.00 | $6,560.00 |
| 30 | P-152 UNCLASSIFIED EXCAVATION & EXPORT | 14,952.00 | CY |
1,400.00
| 0.00 | 1,400.00 | $25.00 | $35,000.00 |
| 31 | P-152 SUBGRADE GRADING AND RECOMPACTION | 120,557.00 | SY |
30,000.00
| 0.00 | 30,000.00 | $1.22 | $36,600.00 |
| 34 | P-208 AGGREGATE BASE COURSE | 21,000.00 | CY |
1,200.00
| 0.00 | 1,200.00 | $50.00 | $60,000.00 |
| 50 | D-701 12" RCP 2500D | 133.00 | LF |
133.00
| 0.00 | 133.00 | $180.00 | $23,940.00 |
| 51 | D-701 18" RCP, 2500D | 352.00 | LF |
197.00
| 0.00 | 197.00 | $144.00 | $28,368.00 |
| 55 | D-751 CATCH BASIN PER STD PLAN 304, 1 GRATE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $7,500.00 | $7,500.00 |
| 56 | D-751 CATCH BASIN PER STD PLAN 304, 1 GRATE (INCLUDING CONCRETE APRON) | 11.00 | EA |
4.00
| 0.00 | 4.00 | $9,700.00 | $38,800.00 |
| 58 | D-751 CONNECT TO EXISTING INLET PER STD PLAN 335 | 4.00 | EA |
2.00
| 0.00 | 2.00 | $2,900.00 | $5,800.00 |
| 59 | D-751 JUNCTION STRUCTURE AT EXISTING STORM DRAIN PER STD PLAN 340 | 2.00 | EA |
2.00
| 0.00 | 2.00 | $5,000.00 | $10,000.00 |
|