| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $20,000.00 | $2,000.00 |
| 5 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 3.00 | EA |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 8 | CONCRETE REMOVAL (NON-REINFORCED) | 52.00 | CY |
55.50
| 52.00 | 3.50 | $177.00 | $619.50 |
| 9 | UNCLASSIFIED EXCAVATION | 880.00 | CY |
888.00
| 880.00 | 8.00 | $64.00 | $512.00 |
| 10 | CRUSHED MISCELLANEOUS BASE | 586.00 | CY |
592.00
| 586.00 | 6.00 | $40.00 | $240.00 |
| 11 | AC PAVEMENT | 530.00 | TON |
544.24
| 530.00 | 14.24 | $97.00 | $1,381.28 |
| 13 | PCC CURB & GUTTER, TYPE A3-8 | 440.00 | LF |
444.50
| 440.00 | 4.50 | $25.60 | $115.20 |
| 14 | PCC WALK, 4" THICK | 240.00 | SF |
410.00
| 240.00 | 170.00 | $12.00 | $2,040.00 |
| 23 | MULTI-AXIAL GEOGRID | 3,600.00 | SY |
3,554.00
| 3,560.00 | -6.00 | $5.35 | ($32.10) |
| S-3 | RESURFACE PAVEMENT | | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| S-4 | RECONSTRUCT C&G AND SIDEWALK | | LS |
1.00
| 0.00 | 1.00 | $4,000.00 | $4,000.00 |