| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) | 10.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.50
| 0.20 | 0.30 | $20,000.00 | $6,000.00 |
| 6 | OFFICE FACILITIES | 10.00 | MTH |
3.00
| 2.00 | 1.00 | $1,500.00 | $1,500.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $375,000.00 | $93,750.00 |
| 11 | S-101 GATE GUARDS / FLAG PERSONS | 190.00 | DAYS |
17.00
| 10.00 | 7.00 | $475.00 | $3,325.00 |
| 12 | P-101 ASPHALT CONCRETE PAVEMENT REMOVAL | 120,654.00 | SY |
69,850.00
| 60,000.00 | 9,850.00 | $1.59 | $15,661.50 |
| 13 | P-101 CONCRETE PAVEMENT REMOVAL | 90.00 | SY |
90.00
| 88.90 | 1.10 | $24.00 | $26.40 |
| 16 | P-101 SAWCUT AC PAVEMENT | 6,702.00 | LF |
1,500.00
| 1,000.00 | 500.00 | $2.50 | $1,250.00 |
| 29 | P-151 CLEARING AND GRUBBING | 1,640.00 | SY |
900.00
| 820.00 | 80.00 | $8.00 | $640.00 |
| 30 | P-152 UNCLASSIFIED EXCAVATION & EXPORT | 14,952.00 | CY |
4,961.00
| 1,400.00 | 3,561.00 | $25.00 | $89,025.00 |
| 31 | P-152 SUBGRADE GRADING AND RECOMPACTION | 120,557.00 | SY |
69,850.00
| 30,000.00 | 39,850.00 | $1.22 | $48,617.00 |
| 34 | P-208 AGGREGATE BASE COURSE | 21,000.00 | CY |
7,700.00
| 1,200.00 | 6,500.00 | $50.00 | $325,000.00 |
| 40 | P-602 BITUMINOUS PRIME COAT | 29,302.00 | GAL |
257.00
| 0.00 | 257.00 | $2.00 | $514.00 |
| 60 | D-754 LONGITUDINAL GUTTER | 2,594.00 | LF |
1,622.00
| 0.00 | 1,622.00 | $49.00 | $79,478.00 |
|