| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.06
| 0.00 | 0.06 | $112,000.00 | $6,720.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
1.00
| 0.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 77 | CONSTRUCT BENCAMP STREET DETOUR RAMP (PLAN RD, SHEET 4) | 1.00 | LS |
0.50
| 0.00 | 0.50 | $104,000.00 | $52,000.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.00
| 0.00 | 1.00 | $15,500.00 | $15,500.00 |