| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) | 10.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.65
| 0.50 | 0.15 | $20,000.00 | $3,000.00 |
| 6 | OFFICE FACILITIES | 10.00 | MTH |
4.00
| 3.00 | 1.00 | $1,500.00 | $1,500.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $375,000.00 | $75,000.00 |
| 8 | S-101 LOW PROFILE BARRICADES PHASE 1 | 2,836.00 | LF |
2,836.00
| 2,420.00 | 416.00 | $22.00 | $9,152.00 |
| 11 | S-101 GATE GUARDS / FLAG PERSONS | 190.00 | DAYS |
29.00
| 17.00 | 12.00 | $475.00 | $5,700.00 |
| 15 | P-101 CONCRETE DIAMOND GRINDING | 2,023.00 | SF |
1,000.00
| 0.00 | 1,000.00 | $3.33 | $3,330.00 |
| 17 | P-101 COLD MILL AC PAVEMENT | 1,042.00 | SY |
610.00
| 0.00 | 610.00 | $18.00 | $10,980.00 |
| 33 | P-154 SUBBASE COURSE | 199.00 | CY |
7.00
| 0.00 | 7.00 | $131.00 | $917.00 |
| 35 | P-208 GRANULAR SHOULDER, 4" THICK | 786.00 | SY |
110.00
| 0.00 | 110.00 | $17.00 | $1,870.00 |
| 36 | P-208 SERVICE ROAD CONNECTOR, 6" THICK | 34.00 | SY |
34.00
| 0.00 | 34.00 | $37.00 | $1,258.00 |
| 37 | P-403 BITUMINOUS SURFACE COURSE | 20,000.00 | TON |
10,000.00
| 0.00 | 10,000.00 | $66.76 | $667,600.00 |
| 40 | P-602 BITUMINOUS PRIME COAT | 29,302.00 | GAL |
12,000.00
| 257.00 | 11,743.00 | $2.00 | $23,486.00 |
| 60 | D-754 LONGITUDINAL GUTTER | 2,594.00 | LF |
1,633.00
| 1,622.00 | 11.00 | $49.00 | $539.00 |
| 64 | H-100 REMOVE AND DISPOSE OF HANGAR ROW "T" | 1.00 | LS |
0.30
| 0.00 | 0.30 | $12,000.00 | $3,600.00 |