Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: San Gabriel Valley Airport Apron Pavement Rehabilitation - Phase 2
Contractor: Griffith Company
3050 East Birch Street
Brea, CA 92821
Project ID: APT5080452
Federal Number(s): None
Original Contract: $5,262,778.28
Awarded: 7/25/2017
Period Ending: 3/22/2018
Board Accepted: 2/20/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH)10.00MTH 4.00 3.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.65 0.500.15$20,000.00$3,000.00
6OFFICE FACILITIES10.00MTH 4.00 3.001.00$1,500.00$1,500.00
7MOBILIZATION1.00LS 0.95 0.750.20$375,000.00$75,000.00
8S-101 LOW PROFILE BARRICADES PHASE 12,836.00LF 2,836.00 2,420.00416.00$22.00$9,152.00
11S-101 GATE GUARDS / FLAG PERSONS190.00DAYS 29.00 17.0012.00$475.00$5,700.00
15P-101 CONCRETE DIAMOND GRINDING2,023.00SF 1,000.00 0.001,000.00$3.33$3,330.00
17P-101 COLD MILL AC PAVEMENT1,042.00SY 610.00 0.00610.00$18.00$10,980.00
33P-154 SUBBASE COURSE199.00CY 7.00 0.007.00$131.00$917.00
35P-208 GRANULAR SHOULDER, 4" THICK786.00SY 110.00 0.00110.00$17.00$1,870.00
36P-208 SERVICE ROAD CONNECTOR, 6" THICK34.00SY 34.00 0.0034.00$37.00$1,258.00
37P-403 BITUMINOUS SURFACE COURSE20,000.00TON 10,000.00 0.0010,000.00$66.76$667,600.00
40P-602 BITUMINOUS PRIME COAT29,302.00GAL 12,000.00 257.0011,743.00$2.00$23,486.00
60D-754 LONGITUDINAL GUTTER2,594.00LF 1,633.00 1,622.0011.00$49.00$539.00
64H-100 REMOVE AND DISPOSE OF HANGAR ROW "T"1.00LS 0.30 0.000.30$12,000.00$3,600.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,121,810.50 $1,313,378.50 $808,432.00
Retained $106,090.53 $65,668.93 $40,421.60
Deducted $0.00 $0.00 $0.00
Due $2,015,719.97 $1,247,709.57 $768,010.40