| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.12
| 0.06 | 0.06 | $112,000.00 | $6,720.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
2.00
| 1.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
2.00
| 1.00 | 1.00 | $5,000.00 | $5,000.00 |
| 20 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $500,000.00 | $250,000.00 |
| 21 | CLEARING AND GRUBBING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $8,000.00 | $4,000.00 |
| 22 | RELOCATE EXISTING BUS SHELTER | 1.00 | EA |
0.50
| 0.00 | 0.50 | $6,000.00 | $3,000.00 |
| 23 | CONCRETE REMOVAL (NON-REINFORCED) | 760.00 | CY |
87.00
| 0.00 | 87.00 | $60.00 | $5,220.00 |
| 28 | BRIDGE REMOVAL (STAGE ONE) | 1.00 | LS |
0.07
| 0.00 | 0.07 | $150,000.00 | $10,500.00 |
| 29 | BRIDGE REMOVAL (STAGE TWO) | 1.00 | LS |
0.10
| 0.00 | 0.10 | $100,000.00 | $10,000.00 |
| 30 | TEMPORARY VERTICAL SHORING (STAGE ONE) | 1.00 | LS |
0.04
| 0.00 | 0.04 | $225,000.00 | $9,000.00 |
| 31 | TEMPORARY VERTICAL SHORING (STAGE TWO) | 1.00 | LS |
0.05
| 0.00 | 0.05 | $200,000.00 | $10,000.00 |
| 32 | TEMPORARY BALLAST (STAGE ONE) | 1.00 | LS |
0.17
| 0.00 | 0.17 | $30,000.00 | $5,100.00 |
| 33 | TEMPORARY BALLAST (STAGE TWO) | 1.00 | LS |
0.50
| 0.00 | 0.50 | $10,000.00 | $5,000.00 |
| 34 | TEMPORARY UTILITY SUPPORT (AT&T CONDUITS) | 1.00 | LS |
0.08
| 0.00 | 0.08 | $60,000.00 | $4,800.00 |
| 35 | UNCLASSIFIED EXCAVATION | 1,299.00 | CY |
62.00
| 0.00 | 62.00 | $35.00 | $2,170.00 |
| 44 | RECONSTRUCT MANHOLE | 3.00 | EA |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |
| 77 | CONSTRUCT BENCAMP STREET DETOUR RAMP (PLAN RD, SHEET 4) | 1.00 | LS |
0.70
| 0.50 | 0.20 | $104,000.00 | $20,800.00 |
| 92 | TRAFFIC CONTROL (STAGE 1) | 1.00 | LS |
0.67
| 0.00 | 0.67 | $11,000.00 | $7,370.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.00
| 0.00 | 1.00 | $5,300.00 | $5,300.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.07
| 1.00 | 0.07 | $15,500.00 | $1,085.00 |
| 101 | HEIGHT RESTRICTION BARRIER | 1.00 | LS |
0.75
| 0.00 | 0.75 | $10,000.00 | $7,500.00 |
| 103 | 3" CONDUIT (SCH 80 PVC) | 80.00 | LF |
80.00
| 0.00 | 80.00 | $93.00 | $7,440.00 |
| 122 | TYPE 332 CABINET FOUNDATION | 1.00 | EA |
1.00
| 0.00 | 1.00 | $1,750.00 | $1,750.00 |
| 150 | DETAIL 27B (ONE-COAT PAINT) | 5,418.00 | LF |
751.00
| 0.00 | 751.00 | $0.25 | $187.75 |
| 174 | FURNISH AND INSTALL UNDERGROUND ELECTRICAL SERVICE CONDUITS AND PULLBOX | 1.00 | LS |
1.00
| 0.00 | 1.00 | $17,000.00 | $17,000.00 |
|