Federal Number(s): None
Original Contract: $195,125.50
Awarded: 11/21/2017
Period Ending: 4/9/2018
Board Accepted: 3/29/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
3CLEARING AND GRUBBING1.00LS 0.80 0.000.80$10,000.00$8,000.00
4CONCRETE REMOVAL (NON-REINFORCED)1.00CY 1.00 0.001.00$400.00$400.00
8STRUCTURE CONCRETE (FOOTING)20.00CY 12.00 0.0012.00$325.00$3,900.00
10SOLAR ELECTRIC POWER ASSEMBLY2.00EA 0.15 0.000.15$16,500.00$2,475.00
13TRENCHING AND SLEEVES FOR ELECTRICAL CONDUIT60.00LF 60.00 0.0060.00$18.00$1,080.00
151" ELECTROLIER LIGHTING CONDUIT70.00LF 60.00 0.0060.00$40.00$2,400.00
17TRAFFIC CONTROL1.00LS 0.25 0.000.25$9,400.00$2,350.00
19CHANGEABLE MESSAGE SIGN1.00EA 1.00 0.001.00$2,900.00$2,900.00
26ROCK VENEER ON MORTAR BED299.00SF 50.00 0.0050.00$18.00$900.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $25,405.00 $0.00 $25,405.00
Retained $1,270.25 $0.00 $1,270.25
Deducted $0.00 $0.00 $0.00
Due $24,134.75 $0.00 $24,134.75