| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) | 9.00 | MTH |
3.00
| 0.00 | 3.00 | $500.00 | $1,500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.18
| 0.12 | 0.06 | $112,000.00 | $6,720.00 |
| 8 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $320.00 | $320.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
3.00
| 2.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
3.00
| 2.00 | 1.00 | $5,000.00 | $5,000.00 |
| 20 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $500,000.00 | $125,000.00 |
| 22 | RELOCATE EXISTING BUS SHELTER | 1.00 | EA |
0.60
| 0.50 | 0.10 | $6,000.00 | $600.00 |
| 23 | CONCRETE REMOVAL (NON-REINFORCED) | 760.00 | CY |
114.00
| 87.00 | 27.00 | $60.00 | $1,620.00 |
| 33 | TEMPORARY BALLAST (STAGE TWO) | 1.00 | LS |
0.00
| 0.50 | -0.50 | $10,000.00 | ($5,000.00) |
| 35 | UNCLASSIFIED EXCAVATION | 1,299.00 | CY |
276.00
| 62.00 | 214.00 | $35.00 | $7,490.00 |
| 41 | CRUSHED MISCELLANEOUS BASE | 898.00 | CY |
196.00
| 0.00 | 196.00 | $40.00 | $7,840.00 |
| 42 | AC PAVEMENT | 1,343.00 | TON |
139.13
| 0.00 | 139.13 | $106.00 | $14,747.78 |
| 43 | AC PAVEMENT(DRIVEWAYS) | 6.00 | TON |
6.00
| 0.00 | 6.00 | $450.00 | $2,700.00 |
| 45 | ADJUST MANHOLE | 3.00 | EA |
1.00
| 0.00 | 1.00 | $960.00 | $960.00 |
| 46 | PCC PAVEMENT | 111.00 | CY |
73.00
| 0.00 | 73.00 | $230.00 | $16,790.00 |
| 67 | PCC CURB, TYPE A1-6 | 21.00 | LF |
7.00
| 0.00 | 7.00 | $80.00 | $560.00 |
| 70 | PCC CURB & GUTTER, TYPE A2-8 | 1,066.00 | LF |
193.00
| 0.00 | 193.00 | $36.00 | $6,948.00 |
| 71 | PCC WALK, 4" THICK | 6,253.00 | SF |
1,425.00
| 0.00 | 1,425.00 | $6.50 | $9,262.50 |
| 72 | PCC CURB RAMP, 4" THICK | 22.00 | SF |
22.00
| 0.00 | 22.00 | $18.00 | $396.00 |
| 73 | PCC DRIVEWAYS, 6" THICK | 886.00 | SF |
78.00
| 0.00 | 78.00 | $9.00 | $702.00 |
| 74 | DETECTABLE WARNING SURFACE | 90.00 | SF |
24.00
| 0.00 | 24.00 | $75.00 | $1,800.00 |
| 76 | CROSS GUTTER | 28.00 | CY |
28.00
| 0.00 | 28.00 | $560.00 | $15,680.00 |
| 77 | CONSTRUCT BENCAMP STREET DETOUR RAMP (PLAN RD, SHEET 4) | 1.00 | LS |
0.90
| 0.70 | 0.20 | $104,000.00 | $20,800.00 |
| 78 | BARRICADE POSTS, STD PLAN W-14 | 1.00 | EA |
1.00
| 0.00 | 1.00 | $930.00 | $930.00 |
| 91 | RELOCATE LIGHT POLE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $8,500.00 | $8,500.00 |
| 92 | TRAFFIC CONTROL (STAGE 1) | 1.00 | LS |
1.00
| 0.67 | 0.33 | $11,000.00 | $3,630.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.14
| 1.07 | 0.07 | $15,500.00 | $1,085.00 |
| 101 | HEIGHT RESTRICTION BARRIER | 1.00 | LS |
0.90
| 0.75 | 0.15 | $10,000.00 | $1,500.00 |
| 105 | 4" CONDUIT (SCH 80 PVC) | 220.00 | LF |
220.00
| 0.00 | 220.00 | $70.00 | $15,400.00 |
| 114 | REMOVE CONTROLLER FOUNDATION | 1.00 | EA |
1.00
| 0.00 | 1.00 | $700.00 | $700.00 |
| 134 | TEMPORARY TRAFFIC SIGNAL SYSTEM AT BENCAMP STREET | 1.00 | LS |
0.85
| 0.00 | 0.85 | $150,000.00 | $127,500.00 |
| 170 | 1-1/2" STREET LIGHT CONDUIT | 40.00 | LF |
30.00
| 0.00 | 30.00 | $58.00 | $1,740.00 |
| 171 | 3" STREET LIGHT CONDUIT | 748.00 | LF |
374.00
| 0.00 | 374.00 | $40.00 | $14,960.00 |
| 173 | NO. 5 PULL BOX INCL PCC COVER (STREET LIGHT) | 10.00 | EA |
5.00
| 0.00 | 5.00 | $500.00 | $2,500.00 |
| 180 | CONCRETE STREET LIGHT FOUNDATION PER STD PLAN 431 | 5.00 | EA |
3.00
| 0.00 | 3.00 | $1,700.00 | $5,100.00 |
| 181 | CONCRETE STREET LIGHT FOUNDATION PER STD PLAN 433 | 2.00 | EA |
1.00
| 0.00 | 1.00 | $1,700.00 | $1,700.00 |
| S-7 | STAGE 1 SIGNAL AT COMMERCIAL CENTER | | LS |
1.00
| 0.00 | 1.00 | $20,780.00 | $20,780.00 |
| S-8 | MODIFY CATCH BASIN DEL MAR AVE STA 10+30 | | LS |
1.00
| 0.00 | 1.00 | $40,000.00 | $40,000.00 |
| S-11 | NORWOOD PLACE CLOSURE AT DEL MAR AVE | | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
|