Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 5/20/2018
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH)9.00MTH 4.00 3.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.24 0.180.06$112,000.00$6,720.00
8IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN6.00MTH 2.00 1.001.00$320.00$320.00
9SURFACE WATER DIVERSION STRUCTURE (STAGE ONE)1.00LS 0.95 0.000.95$100,000.00$95,000.00
14EXCAVATION, TRANSPORTATION, AND DISPOSAL OF LEAD CONTAMINATED SOIL78.00TON 24.00 0.0024.00$130.00$3,120.00
16REMOVAL AND DISPOSAL OF LBP/LCP1.00LS 0.40 0.000.40$54,000.00$21,600.00
18IMPLEMENTATION OF THE SSHSP9.00MTH 4.00 3.001.00$35.00$35.00
19OFFICE FACILITIES9.00MTH 4.00 3.001.00$5,000.00$5,000.00
22RELOCATE EXISTING BUS SHELTER1.00EA 0.90 0.600.30$6,000.00$1,800.00
23CONCRETE REMOVAL (NON-REINFORCED)760.00CY 117.50 114.003.50$60.00$210.00
24CONCRETE REMOVAL (REINFORCED)12.00CY 5.00 0.005.00$214.00$1,070.00
28BRIDGE REMOVAL (STAGE ONE)1.00LS 0.60 0.070.53$150,000.00$79,500.00
30TEMPORARY VERTICAL SHORING (STAGE ONE)1.00LS 0.09 0.040.05$225,000.00$11,250.00
32TEMPORARY BALLAST (STAGE ONE)1.00LS 0.75 0.170.58$30,000.00$17,400.00
35UNCLASSIFIED EXCAVATION1,299.00CY 283.50 276.007.50$35.00$262.50
93TRAFFIC CONTROL (STAGE 2, PHASE 1)1.00LS 0.50 0.000.50$2,100.00$1,050.00
97TEMPORARY RAILING (TYPE K)500.00LF 306.00 0.00306.00$31.00$9,486.00
98TEMPORARY CRASH CUSHION5.00EA 3.00 0.003.00$290.00$870.00
99FLASHING ARROW SIGN2.00EA 1.07 1.000.07$5,300.00$371.00
100CHANGEABLE MESSAGE SIGN3.00EA 1.21 1.140.07$15,500.00$1,085.00
136REMOVE DETAIL 21 (PAINT)3,614.00LF 1,153.00 0.001,153.00$1.00$1,153.00
138REMOVE DETAIL 24 (PAINT)1,859.00LF 120.00 0.00120.00$1.00$120.00
139REMOVE DETAIL 27B (PAINT)5,939.00LF 152.00 0.00152.00$1.00$152.00
142REMOVE DETAIL 38 (PAINT)112.00LF 80.00 0.0080.00$2.50$200.00
145REMOVE PAVEMENT MARKINGS (PAINT)303.00SF 132.00 0.00132.00$2.00$264.00
146REMOVE 12" STRIPING (PAINT)160.00LF 77.00 0.0077.00$2.50$192.50
148DETAIL 21 (ONE-COAT PAINT)2,470.00LF 1,091.00 0.001,091.00$0.55$600.05
149DETAIL 24 (ONE-COAT PAINT)1,859.00LF 92.00 0.0092.00$0.35$32.20
150DETAIL 27B (ONE-COAT PAINT)5,418.00LF 1,692.00 751.00941.00$0.25$235.25
153DETAIL 38A (ONE-COAT PAINT)712.00LF 306.00 0.00306.00$0.75$229.50
162PAVEMENT MARKINGS (ONE-COAT PAINT)178.00SF 148.00 0.00148.00$4.00$592.00
16712" STRIPING (ONE-COAT PAINT)355.00LF 303.00 0.00303.00$3.00$909.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,267,958.03 $1,006,629.03 $261,329.00
Retained $62,022.90 $48,956.45 $13,066.45
Deducted $0.00 $0.00 $0.00
Due $1,205,935.13 $957,672.58 $248,262.55