Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Santa Anita Dam Spillway Modification Project
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001251
Federal Number(s): None
Original Contract: $25,773,160.00
Awarded: 10/18/2017
Period Ending: 6/29/2018
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH)30.00MTH 6.00 5.001.00$750.00$750.00
7IMPLEMENTATION OF THE SWPPP1.00LS 0.33 0.300.03$170,000.00$5,100.00
11OFFICE FACILITIES30.00MTH 6.00 5.001.00$4,000.00$4,000.00
202050-8 REMOVE LADDERS1.00LS 0.25 0.000.25$25,000.00$6,250.00
232050-11 REMOVE CONCRETE BOX AT OUTLET 11.00LS 0.67 0.530.14$15,000.00$2,100.00
252050-13 CUT AND REMOVE PORTIONS OF CONCRETE RISERS1.00LS 0.30 0.000.30$100,000.00$30,000.00
302050-18 CUT AND REMOVE DAM CREST FOR HOIST TAIL TOWER PLATFORM1.00LS 0.69 0.260.43$75,000.00$32,250.00
442140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN1.00LS 0.05 0.0240.026$125,000.00$3,250.00
512200-11 ROCK EXCAVATION (ROAD WIDENING)50.00CY 50.00 48.002.00$2,000.00$4,000.00
583300-2 HOIST TAIL TOWER PLATFORM WITH PARAPET WALLS1.00LS 0.60 0.500.10$150,000.00$15,000.00
603300-4 HOIST LANDING PLATFORM AND CONCRETE RAMP1.00LS 0.05 0.000.05$100,000.00$5,000.00
623300-8 RETAINING WALL (ROAD WIDENING)1.00LS 0.59 0.060.53$175,000.00$92,750.00
9014100-1 CABLEWAY HOIST SYSTEM (COMPLETE)1.00LS 0.15 0.0620.088$1,200,000.00$105,600.00
107ELECTRICAL AND INSTRUMENTATION WORK1.00LS 0.015 0.000.015$2,000,000.00$30,000.00
109SECTION R - UNCLASSIFIED EXCAVATION (ACCESS ROAD AND PARKING AREA PAVEMENT REPLACEMENT)662.00CY 18.00 0.0018.00$115.00$2,070.00
114CHANGEABLE MESSAGE SIGN (EACH)60.00MTH 10.00 8.002.00$1,000.00$2,000.00
S-2MODIFY RETAINING WALL ANCHORS T&M 65,000.00 10,000.0055,000.00$1.00$55,000.00
S-3CONCRETE PUMPING PIPELINE LS 1.00 0.500.50$32,500.00$16,250.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,132,685.20 $721,315.20 $411,370.00
Retained $55,759.26 $35,190.76 $20,568.50
Deducted $0.00 $0.00 $0.00
Due $1,076,925.94 $686,124.44 $390,801.50



Contact Office Engineer
Contractor Copy  