Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 7/20/2018
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH)9.00MTH 6.00 5.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.36 0.300.06$112,000.00$6,720.00
8IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN6.00MTH 4.00 3.001.00$320.00$320.00
9SURFACE WATER DIVERSION STRUCTURE (STAGE ONE)1.00LS 0.97 0.960.01$100,000.00$1,000.00
18IMPLEMENTATION OF THE SSHSP9.00MTH 6.00 5.001.00$35.00$35.00
19OFFICE FACILITIES9.00MTH 6.00 5.001.00$5,000.00$5,000.00
28BRIDGE REMOVAL (STAGE ONE)1.00LS 1.00 0.750.25$150,000.00$37,500.00
32TEMPORARY BALLAST (STAGE ONE)1.00LS 0.77 0.760.01$30,000.00$300.00
36STRUCTURE EXCAVATION (BRIDGE)2,170.00CY 907.00 730.00177.00$37.00$6,549.00
37STRUCTURE BACKFILL (BRIDGE)2,000.00CY 229.00 0.00229.00$50.00$11,450.00
48STRUCTURE CONCRETE (FOOTING)437.00CY 182.00 0.00182.00$300.00$54,600.00
57BAR REINFORCING STEEL (BRIDGE)196,000.00LB 45,558.00 0.0045,558.00$1.18$53,758.44
93TRAFFIC CONTROL (STAGE 2, PHASE 1)1.00LS 0.70 0.600.10$2,100.00$210.00
97TEMPORARY RAILING (TYPE K)500.00LF 324.00 315.009.00$31.00$279.00
99FLASHING ARROW SIGN2.00EA 1.21 1.140.07$5,300.00$371.00
100CHANGEABLE MESSAGE SIGN3.00EA 1.35 1.280.07$15,500.00$1,085.00
S-1CMU BLOCK WALL & CONCRETE REMOVAL AT COMMERCAIL CENTER T&M 5,000.00 0.005,000.00$1.00$5,000.00
S-3ADDITIONAL CONSTRUCTION SIGNS ON DEL MAR AVE T&M 5,800.00 0.005,800.00$1.00$5,800.00
S-4RECONSTRUCT SEWER MANHOLE SOUTHWEST CORNER COMMERCAIL CENTER & DEL MAR AVE T&M 7,000.00 0.007,000.00$1.00$7,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,871,431.13 $1,673,953.69 $197,477.44
Retained $92,196.55 $82,322.68 $9,873.87
Deducted $0.00 $0.00 $0.00
Due $1,779,234.58 $1,591,631.01 $187,603.57