Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: San Gabriel Valley Airport Apron Pavement Rehabilitation - Phase 2
Contractor: Griffith Company
3050 East Birch Street
Brea, CA 92821
Project ID: APT5080452
Federal Number(s): None
Original Contract: $5,262,778.28
Awarded: 7/25/2017
Period Ending: 7/26/2018
Board Accepted: 2/20/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH)10.00MTH 8.00 7.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.85 0.800.05$20,000.00$1,000.00
6OFFICE FACILITIES10.00MTH 7.00 6.001.00$1,500.00$1,500.00
11S-101 GATE GUARDS / FLAG PERSONS190.00DAYS 52.00 45.007.00$475.00$3,325.00
12P-101 ASPHALT CONCRETE PAVEMENT REMOVAL120,654.00SY 10,800.00 98,150.00-87,350.00$1.59($138,886.50)
30P-152 UNCLASSIFIED EXCAVATION & EXPORT14,952.00CY 11,000.00 4,961.006,039.00$25.00$150,975.00
31P-152 SUBGRADE GRADING AND RECOMPACTION120,557.00SY 100,000.00 69,850.0030,150.00$1.22$36,783.00
33P-154 SUBBASE COURSE199.00CY 28.00 24.004.00$131.00$524.00
34P-208 AGGREGATE BASE COURSE21,000.00CY 9,500.00 7,762.001,738.00$50.00$86,900.00
60D-754 LONGITUDINAL GUTTER2,594.00LF 1,933.00 1,633.00300.00$49.00$14,700.00
S-3D-754 LONGITUDINAL LF 830.00 0.00830.00$97.50$80,925.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,673,406.04 $3,435,160.54 $238,245.50
Retained $183,670.30 $171,758.03 $11,912.27
Deducted $0.00 $0.00 $0.00
Due $3,489,735.74 $3,263,402.51 $226,333.23



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.