| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH) | 10.00 | MTH |
9.00
| 8.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.85 | 0.05 | $20,000.00 | $1,000.00 |
| 6 | OFFICE FACILITIES | 10.00 | MTH |
9.00
| 7.00 | 2.00 | $1,500.00 | $3,000.00 |
| 11 | S-101 GATE GUARDS / FLAG PERSONS | 190.00 | DAYS |
62.00
| 52.00 | 10.00 | $475.00 | $4,750.00 |
| 12 | P-101 ASPHALT CONCRETE PAVEMENT REMOVAL | 120,654.00 | SY |
108,129.00
| 10,800.00 | 97,329.00 | $1.59 | $154,753.11 |
| 17 | P-101 COLD MILL AC PAVEMENT | 1,042.00 | SY |
1,042.00
| 610.00 | 432.00 | $18.00 | $7,776.00 |
| 30 | P-152 UNCLASSIFIED EXCAVATION & EXPORT | 14,952.00 | CY |
13,000.00
| 11,000.00 | 2,000.00 | $25.00 | $50,000.00 |
| 31 | P-152 SUBGRADE GRADING AND RECOMPACTION | 120,557.00 | SY |
108,129.00
| 100,000.00 | 8,129.00 | $1.22 | $9,917.38 |
| 33 | P-154 SUBBASE COURSE | 199.00 | CY |
50.00
| 28.00 | 22.00 | $131.00 | $2,882.00 |
| 34 | P-208 AGGREGATE BASE COURSE | 21,000.00 | CY |
15,240.00
| 9,500.00 | 5,740.00 | $50.00 | $287,000.00 |
| 35 | P-208 GRANULAR SHOULDER, 4" THICK | 786.00 | SY |
786.00
| 110.00 | 676.00 | $17.00 | $11,492.00 |
| 37 | P-403 BITUMINOUS SURFACE COURSE | 20,000.00 | TON |
11,800.00
| 11,385.00 | 415.00 | $66.76 | $27,705.40 |
| 60 | D-754 LONGITUDINAL GUTTER | 2,594.00 | LF |
2,944.64
| 1,933.00 | 1,011.64 | $49.00 | $49,570.36 |
| S-2 | UNKNOWN UTILITY LINE INVESTIGATION | | T&M |
2,500.00
| 798.20 | 1,701.80 | $1.00 | $1,701.80 |
| S-2A | UNKNOWN UTILITY LINE INIVESTIGATION | | T&M |
1,275.93
| 0.00 | 1,275.93 | $1.00 | $1,275.93 |
| S-3 | D-754 LONGITUDINAL | | LF |
1,234.00
| 830.00 | 404.00 | $97.50 | $39,390.00 |
| S-4 | 4" TRANSITION GUTTER | | SF |
207.00
| 0.00 | 207.00 | $12.25 | $2,535.75 |
|