Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: San Gabriel Valley Airport Apron Pavement Rehabilitation - Phase 2
Contractor: Griffith Company
3050 East Birch Street
Brea, CA 92821
Project ID: APT5080452
Federal Number(s): None
Original Contract: $5,262,778.28
Awarded: 7/25/2017
Period Ending: 8/22/2018
Board Accepted: 2/20/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH)10.00MTH 9.00 8.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.90 0.850.05$20,000.00$1,000.00
6OFFICE FACILITIES10.00MTH 9.00 7.002.00$1,500.00$3,000.00
11S-101 GATE GUARDS / FLAG PERSONS190.00DAYS 62.00 52.0010.00$475.00$4,750.00
12P-101 ASPHALT CONCRETE PAVEMENT REMOVAL120,654.00SY 108,129.00 10,800.0097,329.00$1.59$154,753.11
17P-101 COLD MILL AC PAVEMENT1,042.00SY 1,042.00 610.00432.00$18.00$7,776.00
30P-152 UNCLASSIFIED EXCAVATION & EXPORT14,952.00CY 13,000.00 11,000.002,000.00$25.00$50,000.00
31P-152 SUBGRADE GRADING AND RECOMPACTION120,557.00SY 108,129.00 100,000.008,129.00$1.22$9,917.38
33P-154 SUBBASE COURSE199.00CY 50.00 28.0022.00$131.00$2,882.00
34P-208 AGGREGATE BASE COURSE21,000.00CY 15,240.00 9,500.005,740.00$50.00$287,000.00
35P-208 GRANULAR SHOULDER, 4" THICK786.00SY 786.00 110.00676.00$17.00$11,492.00
37P-403 BITUMINOUS SURFACE COURSE20,000.00TON 11,800.00 11,385.00415.00$66.76$27,705.40
60D-754 LONGITUDINAL GUTTER2,594.00LF 2,944.64 1,933.001,011.64$49.00$49,570.36
S-2UNKNOWN UTILITY LINE INVESTIGATION T&M 2,500.00 798.201,701.80$1.00$1,701.80
S-2AUNKNOWN UTILITY LINE INIVESTIGATION T&M 1,275.93 0.001,275.93$1.00$1,275.93
S-3D-754 LONGITUDINAL LF 1,234.00 830.00404.00$97.50$39,390.00
S-44" TRANSITION GUTTER SF 207.00 0.00207.00$12.25$2,535.75

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,328,655.77 $3,673,406.04 $655,249.73
Retained $216,432.80 $183,670.30 $32,762.50
Deducted $0.00 $0.00 $0.00
Due $4,112,222.97 $3,489,735.74 $622,487.23



Contact Office Engineer
Contractor Copy  