| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) | 9.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.42
| 0.36 | 0.06 | $112,000.00 | $6,720.00 |
| 8 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 6.00 | MTH |
5.00
| 4.00 | 1.00 | $320.00 | $320.00 |
| 9 | SURFACE WATER DIVERSION STRUCTURE (STAGE ONE) | 1.00 | LS |
0.98
| 0.97 | 0.01 | $100,000.00 | $1,000.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
7.00
| 6.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
7.00
| 6.00 | 1.00 | $5,000.00 | $5,000.00 |
| 30 | TEMPORARY VERTICAL SHORING (STAGE ONE) | 1.00 | LS |
0.97
| 0.80 | 0.17 | $225,000.00 | $38,250.00 |
| 32 | TEMPORARY BALLAST (STAGE ONE) | 1.00 | LS |
0.78
| 0.77 | 0.01 | $30,000.00 | $300.00 |
| 34 | TEMPORARY UTILITY SUPPORT (AT&T CONDUITS) | 1.00 | LS |
1.00
| 0.75 | 0.25 | $60,000.00 | $15,000.00 |
| 37 | STRUCTURE BACKFILL (BRIDGE) | 2,000.00 | CY |
666.00
| 229.00 | 437.00 | $50.00 | $21,850.00 |
| 38 | FILTER MATERIAL (CEMENT TREATED PERMEABLE BASE) | 8.00 | CY |
3.00
| 0.00 | 3.00 | $330.00 | $990.00 |
| 39 | FILTER FABRIC | 76.00 | SY |
31.00
| 0.00 | 31.00 | $23.00 | $713.00 |
| 40 | GEOCOMPOSITE WALL DRAIN | 4,860.00 | SF |
1,601.00
| 0.00 | 1,601.00 | $6.00 | $9,606.00 |
| 47 | STRUCTURE CONCRETE (BRIDGE) | 734.00 | CY |
165.00
| 0.00 | 165.00 | $895.00 | $147,675.00 |
| 57 | BAR REINFORCING STEEL (BRIDGE) | 196,000.00 | LB |
60,058.00
| 45,558.00 | 14,500.00 | $1.18 | $17,110.00 |
| 65 | ERECT PRESTRESSED GIRDERS | 17.00 | EA |
7.00
| 0.00 | 7.00 | $2,000.00 | $14,000.00 |
| 66 | FURNISH PRESTRESSED I GIRDERS, 80' LONG | 17.00 | EA |
7.00
| 0.00 | 7.00 | $17,600.00 | $123,200.00 |
| 88 | 3" PVC SCH 80 DRAIN PIPE | 371.00 | LF |
152.00
| 0.00 | 152.00 | $12.00 | $1,824.00 |
| 89 | 4" PVC SCH 80 DRAIN PIPE | 64.00 | LF |
26.00
| 0.00 | 26.00 | $30.00 | $780.00 |
| 93 | TRAFFIC CONTROL (STAGE 2, PHASE 1) | 1.00 | LS |
0.80
| 0.70 | 0.10 | $2,100.00 | $210.00 |
| 97 | TEMPORARY RAILING (TYPE K) | 500.00 | LF |
333.00
| 324.00 | 9.00 | $31.00 | $279.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.28
| 1.21 | 0.07 | $5,300.00 | $371.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.42
| 1.35 | 0.07 | $15,500.00 | $1,085.00 |
| S-2 | REPLACE 33"X54" SEWER MANHOLE COVER AT COMMERCAIL CENTER | | T&M |
3,975.78
| 0.00 | 3,975.78 | $1.00 | $3,975.78 |
| S-20 | HANDICAP RAMPS AT PARK & RIDE | | T&M |
12,060.35
| 8,325.39 | 3,734.96 | $1.00 | $3,734.96 |
| S-23 | REMOVAL OF EXISTING WINGWALL | | T&M |
7,915.63
| 0.00 | 7,915.63 | $1.00 | $7,915.63 |
| S-24A | REPLACE EXISTING RESTRICTION BARRIER AT BENCAMP | | LS |
1.00
| 0.00 | 1.00 | $13,500.00 | $13,500.00 |
|