Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 9/20/2018
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH)9.00MTH 8.00 7.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.48 0.420.06$112,000.00$6,720.00
8IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN6.00MTH 6.00 5.001.00$320.00$320.00
9SURFACE WATER DIVERSION STRUCTURE (STAGE ONE)1.00LS 0.99 0.980.01$100,000.00$1,000.00
18IMPLEMENTATION OF THE SSHSP9.00MTH 8.00 7.001.00$35.00$35.00
19OFFICE FACILITIES9.00MTH 8.00 7.001.00$5,000.00$5,000.00
23CONCRETE REMOVAL (NON-REINFORCED)760.00CY 165.50 117.5048.00$60.00$2,880.00
32TEMPORARY BALLAST (STAGE ONE)1.00LS 0.79 0.780.01$30,000.00$300.00
35UNCLASSIFIED EXCAVATION1,299.00CY 403.50 283.50120.00$35.00$4,200.00
37STRUCTURE BACKFILL (BRIDGE)2,000.00CY 820.00 666.00154.00$50.00$7,700.00
38FILTER MATERIAL (CEMENT TREATED PERMEABLE BASE)8.00CY 3.50 3.000.50$330.00$165.00
40GEOCOMPOSITE WALL DRAIN4,860.00SF 1,913.00 1,601.00312.00$6.00$1,872.00
47STRUCTURE CONCRETE (BRIDGE)734.00CY 303.00 165.00138.00$895.00$123,510.00
49MINOR CONCRETE (DRAINAGE PAD)2.00CY 0.25 0.000.25$1,900.00$475.00
57BAR REINFORCING STEEL (BRIDGE)196,000.00LB 79,701.00 60,058.0019,643.00$1.18$23,178.74
883" PVC SCH 80 DRAIN PIPE371.00LF 168.00 152.0016.00$12.00$192.00
93TRAFFIC CONTROL (STAGE 2, PHASE 1)1.00LS 0.90 0.800.10$2,100.00$210.00
97TEMPORARY RAILING (TYPE K)500.00LF 342.00 333.009.00$31.00$279.00
99FLASHING ARROW SIGN2.00EA 1.35 1.280.07$5,300.00$371.00
S-1CMU BLOCK WALL & CONCRETE REMOVAL AT COMMERCAIL CENTER T&M 5,338.68 5,000.00338.68$1.00$338.68
S-3ADDITIONAL CONSTRUCTION SIGNS ON DEL MAR AVE T&M 9,470.83 5,800.003,670.83$1.00$3,670.83
S-19HIGH EARLY STRENGTH CONCRETE T&M 1,443.55 0.001,443.55$1.00$1,443.55

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,491,736.30 $2,307,375.50 $184,360.80
Retained $123,211.81 $113,993.77 $9,218.04
Deducted $0.00 $0.00 $0.00
Due $2,368,524.49 $2,193,381.73 $175,142.76