| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) | 9.00 | MTH |
8.00
| 7.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.48
| 0.42 | 0.06 | $112,000.00 | $6,720.00 |
| 8 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $320.00 | $320.00 |
| 9 | SURFACE WATER DIVERSION STRUCTURE (STAGE ONE) | 1.00 | LS |
0.99
| 0.98 | 0.01 | $100,000.00 | $1,000.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
8.00
| 7.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
8.00
| 7.00 | 1.00 | $5,000.00 | $5,000.00 |
| 23 | CONCRETE REMOVAL (NON-REINFORCED) | 760.00 | CY |
165.50
| 117.50 | 48.00 | $60.00 | $2,880.00 |
| 32 | TEMPORARY BALLAST (STAGE ONE) | 1.00 | LS |
0.79
| 0.78 | 0.01 | $30,000.00 | $300.00 |
| 35 | UNCLASSIFIED EXCAVATION | 1,299.00 | CY |
403.50
| 283.50 | 120.00 | $35.00 | $4,200.00 |
| 37 | STRUCTURE BACKFILL (BRIDGE) | 2,000.00 | CY |
820.00
| 666.00 | 154.00 | $50.00 | $7,700.00 |
| 38 | FILTER MATERIAL (CEMENT TREATED PERMEABLE BASE) | 8.00 | CY |
3.50
| 3.00 | 0.50 | $330.00 | $165.00 |
| 40 | GEOCOMPOSITE WALL DRAIN | 4,860.00 | SF |
1,913.00
| 1,601.00 | 312.00 | $6.00 | $1,872.00 |
| 47 | STRUCTURE CONCRETE (BRIDGE) | 734.00 | CY |
303.00
| 165.00 | 138.00 | $895.00 | $123,510.00 |
| 49 | MINOR CONCRETE (DRAINAGE PAD) | 2.00 | CY |
0.25
| 0.00 | 0.25 | $1,900.00 | $475.00 |
| 57 | BAR REINFORCING STEEL (BRIDGE) | 196,000.00 | LB |
79,701.00
| 60,058.00 | 19,643.00 | $1.18 | $23,178.74 |
| 88 | 3" PVC SCH 80 DRAIN PIPE | 371.00 | LF |
168.00
| 152.00 | 16.00 | $12.00 | $192.00 |
| 93 | TRAFFIC CONTROL (STAGE 2, PHASE 1) | 1.00 | LS |
0.90
| 0.80 | 0.10 | $2,100.00 | $210.00 |
| 97 | TEMPORARY RAILING (TYPE K) | 500.00 | LF |
342.00
| 333.00 | 9.00 | $31.00 | $279.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.35
| 1.28 | 0.07 | $5,300.00 | $371.00 |
| S-1 | CMU BLOCK WALL & CONCRETE REMOVAL AT COMMERCAIL CENTER | | T&M |
5,338.68
| 5,000.00 | 338.68 | $1.00 | $338.68 |
| S-3 | ADDITIONAL CONSTRUCTION SIGNS ON DEL MAR AVE | | T&M |
9,470.83
| 5,800.00 | 3,670.83 | $1.00 | $3,670.83 |
| S-19 | HIGH EARLY STRENGTH CONCRETE | | T&M |
1,443.55
| 0.00 | 1,443.55 | $1.00 | $1,443.55 |